<front>
<journal-meta>
<journal-id journal-id-type="publisher-id">JTSCM</journal-id>
<journal-title-group>
<journal-title>Journal of Transport and Supply Chain Management</journal-title>
</journal-title-group>
<issn pub-type="ppub">2310-8789</issn>
<issn pub-type="epub">1995-5235</issn>
<publisher>
<publisher-name>AOSIS</publisher-name>
</publisher>
</journal-meta>
<article-meta>
<article-id pub-id-type="publisher-id">JTSCM-16-733</article-id>
<article-id pub-id-type="doi">10.4102/jtscm.v16i0.733</article-id>
<article-categories>
<subj-group subj-group-type="heading">
<subject>Original Research</subject>
</subj-group>
</article-categories>
<title-group>
<article-title>The state of South Africa&#x2019;s public&#x2013;private partnership practices in transport projects: Problems and potential</article-title>
</title-group>
<contrib-group>
<contrib contrib-type="author" corresp="yes">
<contrib-id contrib-id-type="orcid">https://orcid.org/0000-0003-1247-0731</contrib-id>
<name>
<surname>Sebitlo</surname>
<given-names>Ofentse K.</given-names>
</name>
<xref ref-type="aff" rid="AF0001">1</xref>
</contrib>
<contrib contrib-type="author">
<contrib-id contrib-id-type="orcid">https://orcid.org/0000-0001-8775-0215</contrib-id>
<name>
<surname>Mbara</surname>
<given-names>Tatenda</given-names>
</name>
<xref ref-type="aff" rid="AF0001">1</xref>
</contrib>
<contrib contrib-type="author">
<contrib-id contrib-id-type="orcid">https://orcid.org/0000-0003-1915-6956</contrib-id>
<name>
<surname>Luke</surname>
<given-names>Rose</given-names>
</name>
<xref ref-type="aff" rid="AF0001">1</xref>
</contrib>
<aff id="AF0001"><label>1</label>Department of Transport and Supply Chain Management, School of Management, University of Johannesburg, Johannesburg, South Africa</aff>
</contrib-group>
<author-notes>
<corresp id="cor1"><bold>Corresponding author:</bold> Ofentse Sebitlo, <email xlink:href="sebitlo.ofentse@gmail.com">sebitlo.ofentse@gmail.com</email></corresp>
</author-notes>
<pub-date pub-type="epub"><day>06</day><month>12</month><year>2022</year></pub-date>
<pub-date pub-type="collection"><year>2022</year></pub-date>
<volume>16</volume>
<elocation-id>733</elocation-id>
<history>
<date date-type="received"><day>10</day><month>01</month><year>2022</year></date>
<date date-type="accepted"><day>26</day><month>06</month><year>2022</year></date>
</history>
<permissions>
<copyright-statement>&#x00A9; 2022. The Authors</copyright-statement>
<copyright-year>2022</copyright-year>
<license license-type="open-access" xlink:href="https://creativecommons.org/licenses/by/4.0/">
<license-p>Licensee: AOSIS. This work is licensed under the Creative Commons Attribution License.</license-p>
</license>
</permissions>
<abstract>
<sec id="st1">
<title>Background</title>
<p>Despite growing calls for public&#x2013;private partnerships (PPPs) to supplement diminishing investment in South Africa&#x2019;s transport sector, the uptake of transport PPPs in the country was low over the past 15 years compared with Brazil, Russia, India and China which performed well in this regard. This low uptake poses several consequences in light of the positive correlation between transport capital investment and economic growth.</p>
</sec>
<sec id="st2">
<title>Objectives</title>
<p>The study aimed to describe the problems faced in the South African PPP process, firstly by comparing and contrasting PPP practices of South Africa to its counterparts in the Brazil, Russia, India, China and South Africa (BRICS) multilateral forum in view of understanding the reasons for the low uptake of transport PPPs in the country and, secondly, by interviewing transport PPP experts on their opinions on constraints and possible solutions for PPPs in the country.</p>
</sec>
<sec id="st3">
<title>Method</title>
<p>In light of the limited research on transport PPPs in South Africa, as well as the low level of PPP implementation, secondary data analysis was followed by an exploratory qualitative research design used to obtain rich data from subject experts on the topic at hand.</p>
</sec>
<sec id="st4">
<title>Results</title>
<p>The main findings reveal that the politicisation of infrastructure through party politics, political risk and domination of the state in the delivery of strategic infrastructure contributes to the low uptake of PPPs.</p>
</sec>
<sec id="st5">
<title>Conclusion</title>
<p>A need exists to strengthen political commitment for PPPs by centralising and coordinating planning across different tiers of government, while easing the regulatory burden, making them simpler to implement and more attractive to investors and promoting inclusivity. Policymakers can utilise these findings to improve areas of practice requiring intervention.</p>
</sec>
</abstract>
<kwd-group>
<kwd>public&#x2013;private partnership practices</kwd>
<kwd>transport sector</kwd>
<kwd>South Africa</kwd>
<kwd>BRICS</kwd>
<kwd>best practice</kwd>
</kwd-group>
</article-meta>
</front>
<body>
<sec id="s0001">
<title>Introduction</title>
<p>Over the past 20 years, there have been growing calls in South Africa by policymakers and executives of state-owned enterprises to improve the level of joint investment and partnership by the public and private sectors in the country&#x2019;s major capital projects (Ittmann <xref ref-type="bibr" rid="CIT0031">2017</xref>; Sinkala et al. <xref ref-type="bibr" rid="CIT0062">2021</xref>; Walwyn &#x0026; Nkolele <xref ref-type="bibr" rid="CIT0073">2018</xref>). These calls were made as a result of concerns regarding the impact of the budget deficit on priorities of the state, such as transport capital investment and the consequences it poses for economic growth (Ittmann <xref ref-type="bibr" rid="CIT0031">2017</xref>). Specifically, the call made by the South African Minister of Finance during the 2016 budget speech could be regarded as one of the most significant pronouncements by the public sector. Unlike previous calls, the Minister made an unequivocal appeal for joint investments in clearly defined capital projects (National Treasury <xref ref-type="bibr" rid="CIT0048">2016</xref>). The minister indicated that without joint investment, the financing of capital projects will increasingly prove to be a challenge because of growing fiscal constraints (National Treasury <xref ref-type="bibr" rid="CIT0048">2016</xref>). This call was restated by the President of the Republic during a meeting with leaders of business and developmental finance institutions when he directed that an infrastructure investment plan be developed that &#x2018;outlines a public-private partnership framework and removes policy bottlenecks in engaging with the private sector&#x2019; (The Presidency <xref ref-type="bibr" rid="CIT0068">2020</xref>: para. 39). In this regard, public&#x2013;private partnerships (PPPs) in capital projects are widely regarded as a viable option for bridging this deficit by augmenting deficiencies within the public sector budget with private capital (Arimoro <xref ref-type="bibr" rid="CIT0005">2018</xref>).</p>
<p>There is no universally accepted definition of a PPP (Arimoro <xref ref-type="bibr" rid="CIT0005">2018</xref>; Koskela, Rooke &#x0026; Siriwardena <xref ref-type="bibr" rid="CIT0034">2016</xref>; World Bank Group [WBG] <xref ref-type="bibr" rid="CIT0078">2015a</xref>). For instance, in Brazil, PPP refers to &#x2018;contracts between the government and private sector entities for the purpose of the joint execution or provision of a project or a service traditionally handled by the public sector&#x2019; (Queiroz, Astesiano &#x0026; Serebrinsky <xref ref-type="bibr" rid="CIT0057">2014</xref>:12). Russia defines PPP as:</p>
<disp-quote>
<p>[<italic>C</italic>]ooperation of a public partner (the Russian Federation, a region or a municipal authority) and a private partner (a Russian legal entity) on the basis of a PPP agreement entered into pursuant to a tender procedure and aimed at increasing the quality and availability of public services by attracting private investment. (Marquaire <xref ref-type="bibr" rid="CIT0043">2020</xref>:213&#x2013;214)</p>
</disp-quote>
<p>In comparison, PPP in India means a project based on a contract or concession agreement between a government or statutory entity on the one side and a private sector company on the other side for delivering an infrastructure service on payment of user charges (WSP International Management Consulting <xref ref-type="bibr" rid="CIT0083">n.d.</xref>:3). China defines PPPs as &#x2018;long-term contractual collaborations between the government and societal capital in the areas of infrastructure and public services (Tan &#x0026; Zhao <xref ref-type="bibr" rid="CIT0064">2019</xref>:1).&#x2019; South Africa refers to PPPs as:</p>
<disp-quote>
<p>[<italic>A</italic>] contract between a public-sector institution and a private party, where the private party performs a function that is usually provided by the public sector and/or uses state property in terms of the PPP agreement. (National Treasury <xref ref-type="bibr" rid="CIT0050">2021</xref>:167)</p>
</disp-quote>
<p>In all instances, the commonality in the definitions of these countries includes the recognition of PPP as a contract or legal agreement between the public and private sectors, wherein the private sector substitutes the public sector in the provision of a public service or good. This indicates that PPPs are legally binding and need to be in the interest of the public. It is also apparent that PPPs in all the BRICS countries (Brazil, Russia, India, China and South Africa) are characterised by the significant transfer of operational, financial and technical risk to the private sector (Marquaire <xref ref-type="bibr" rid="CIT0043">2020</xref>; National Treasury <xref ref-type="bibr" rid="CIT0050">2021</xref>; Queiroz et al. <xref ref-type="bibr" rid="CIT0057">2014</xref>; Tan &#x0026; Zhao <xref ref-type="bibr" rid="CIT0064">2019</xref>; WSP International Management Consulting <xref ref-type="bibr" rid="CIT0083">n.d.</xref>).</p>
<p>Some differences in the definitions are also observed. For example, Russia&#x2019;s definition differs from the rest as it indicates that a PPP agreement is a product of a tender process (Marquaire <xref ref-type="bibr" rid="CIT0043">2020</xref>), which shows that competitive bidding is prioritised for PPP procurement in this country. India&#x2019;s definition reveals that payment is conducted through user charges (WSP International Management Consulting <xref ref-type="bibr" rid="CIT0083">n.d.</xref>), which indicates that user charges are the main mode for the generation of revenue. Unlike the other countries, China&#x2019;s definition specifies that the contract period should be long term (Tan &#x0026; Zhao <xref ref-type="bibr" rid="CIT0064">2019</xref>), which demonstrates that China prioritises projects that offer greater stability and predictability. The South African definition indicates the substitution of a public function by a private party and use of state property in terms of the PPP agreement (National Treasury <xref ref-type="bibr" rid="CIT0050">2021</xref>), which shows that assets not owned by the state and services not typically provided by the state are mostly excluded from these agreements; however, an exception to this rule exists. Based on these definitions, the parameters for a PPP therefore include an agreement between the public and private sector, long-term contract periods, competitive bidding, payment through user-pays, assets owned by the state and a function typically performed by the state.</p>
<p>The growing popularity of this form of procurement across the BRICS countries and the rest of the world can be attributed to the benefits arising from their inherent ability to allow the public sector to leverage private capital and expertise in a manner that yields value for money, affordability and appropriate transfer of risk in the delivery of much-needed capital projects (Arimoro <xref ref-type="bibr" rid="CIT0005">2018</xref>; Churakov <xref ref-type="bibr" rid="CIT0012">2014</xref>; Gopalkrishna &#x0026; Karnam <xref ref-type="bibr" rid="CIT0021">2015</xref>; Koskela et al. <xref ref-type="bibr" rid="CIT0034">2016</xref>; Mouraviev &#x0026; Kakabadse <xref ref-type="bibr" rid="CIT0046">2014</xref>). Public&#x2013;private partnerships are also recognised for their ability to promote regular maintenance of infrastructure over the long term, as this is usually incorporated as a general requirement for such projects (Gopalkrishna &#x0026; Karnam <xref ref-type="bibr" rid="CIT0021">2015</xref>). The literature also shows that there exist some inherent disadvantages associated with PPPs, such as the prohibitive amount of time, capital and effort that is usually required to obtain the necessary approvals and support from the relevant authorities for implementation (Churakov <xref ref-type="bibr" rid="CIT0012">2014</xref>; Government Technical Advisory Centre [GTAC] <xref ref-type="bibr" rid="CIT0023">2016</xref>; Sanni &#x0026; Hashim <xref ref-type="bibr" rid="CIT0060">2014</xref>; Thomassen et al. <xref ref-type="bibr" rid="CIT0071">2016</xref>). For instance, the limited capacity of officials to prepare a compelling business case that conforms to regulatory requirements can result in delays (GTAC <xref ref-type="bibr" rid="CIT0023">2016</xref>; Sanni &#x0026; Hashim <xref ref-type="bibr" rid="CIT0060">2014</xref>; Thomassen et al. <xref ref-type="bibr" rid="CIT0071">2016</xref>). Transaction advisors are then typically appointed at a high cost to the state to assist in &#x2018;understanding the different forms of economic organisation and contractual arrangements required in obtaining regulatory approval&#x2019; (Thomassen et al. <xref ref-type="bibr" rid="CIT0071">2016</xref>:820).</p>
<p>An inspection of the World Bank&#x2019;s Private Participation in Infrastructure Database (WBG <xref ref-type="bibr" rid="CIT0080">2019</xref>) and the PPP database of the GTAC (<xref ref-type="bibr" rid="CIT0024">2019</xref>) reveal that South Africa has not been able to emulate the performance of the four largest developing countries on the uptake of PPPs in the transport sector. The disparity in the performance of South Africa compared with its BRICS counterparts is demonstrated in <xref ref-type="fig" rid="F0001">Figure 1</xref>, which shows the number of transport PPPs to reach financial closure over the past 15 years.</p>
<fig id="F0001">
<label>FIGURE 1</label>
<caption><p>Number of transport public&#x2013;private partnerships that have reached financial closure in the BRICS countries over the past 15 years.</p></caption>
<graphic xmlns:xlink="http://www.w3.org/1999/xlink" xlink:href="JTSCM-16-733-g001.tif"/>
</fig>
<p>Whilst the sizes of the economies make comparisons difficult, <xref ref-type="fig" rid="F0001">Figure 1</xref> illustrates the relatively low level of PPP implementation in South Africa, despite calls for a higher level of private sector participation in major infrastructure projects. Of these countries, China has the largest economy with a gross domestic product (GDP) of about USD15.47 trillion, followed by India at USD3.26 tn, Brazil at USD2.06 tn, Russia at USD1.67 tn and South Africa with the smallest economy at USD386.73 bn (World Population Review <xref ref-type="bibr" rid="CIT0081">2019</xref>). A comparison of GDP per capita shows that Russia is ranked highest at USD11.436, followed by China at USD10.679, then Brazil at USD9.577, South Africa at USD6.365 and India at USD2.316 (World Population Review <xref ref-type="bibr" rid="CIT0081">2019</xref>). Even with the relative success of a major PPP such as the Gautrain Rapid Rail project (Gautrain), which is regarded as the largest PPP on African soil (Ittmann <xref ref-type="bibr" rid="CIT0031">2017</xref>), this does not appear to have bolstered the demand for transport PPPs in South Africa. The other two projects to reach financial closure in South Africa over the period under review include the bridge at Beitbridge Border Post by the New Limpopo Bridge Limited and the Durban Passenger Terminal by MSC Cruises (GTAC <xref ref-type="bibr" rid="CIT0024">2019</xref>; WBG <xref ref-type="bibr" rid="CIT0080">2019</xref>). Based on the definition parameters adopted here, some of the success factors for these projects include long-term contract periods, competitive bidding and payment through user-pay, as is evidenced by the Durban Passenger Terminal with a contract period of 25 years, followed by the Gautrain project at 20 years and the Beitbridge Border Post at 15 years (GTAC <xref ref-type="bibr" rid="CIT0024">2019</xref>; WBG <xref ref-type="bibr" rid="CIT0080">2019</xref>). The Durban Passenger Terminal and Gautrain projects both entail competitive bidding, whilst the main revenue source for the Beitbridge Border Post and Gautrain projects is user-pay (WBG <xref ref-type="bibr" rid="CIT0080">2019</xref>). Although the Gautrain project is categorised as a PPP, there is criticism as to whether it deserves to be regarded as such, given the low financial risk to the private sector, as most of the funds for the project emanate from the provincial government (Dachs <xref ref-type="bibr" rid="CIT0014">2011</xref>; National Treasury <xref ref-type="bibr" rid="CIT0049">2017</xref>). In comparison, the Beitbridge Border Post, which has transferred most of the financial risk to the private sector (WBG <xref ref-type="bibr" rid="CIT0080">2019</xref>), deserves to be categorised as a PPP.</p>
<p>In light of the given discussion, this article seeks to describe the problems faced in the South African PPP process, firstly by comparing PPP practices in South Africa to those used by its BRICS counterparts in view of understanding the reasons for the low uptake of transport PPPs in the country and, secondly, to solicit opinions from transport PPP experts on factors that inhibit the uptake of PPPs in the country and recommendations on improvements required to facilitate the uptake. A comparative analysis is important as it could reveal new findings and insights based on the experience of other upper middle-income countries with similar developmental challenges. This view is reinforced by Sanni and Hashim (<xref ref-type="bibr" rid="CIT0060">2014</xref>), who question the adoption of systems from developed economies for the promotion of PPPs in sub-Saharan or developing countries. This suggests that countries such as South Africa, which tend to focus on the experiences of developed nations, might be overlooking systems or practices of other comparable developing countries that are yielding positive results (Leighland <xref ref-type="bibr" rid="CIT0036">2018</xref>). Policymakers can utilise these findings to improve areas of practice requiring intervention.</p>
<p>A background to the research is provided in the next section, focusing on a review of literature on PPP practices in the BRICS countries and best practices. This is followed by a description of the research method and design. The findings of the study and discussion thereof are then provided. Finally, based on the findings, a conclusion is then drawn and recommendations for policy improvement and further research identified.</p>
</sec>
<sec id="s0002">
<title>Background</title>
<sec id="s20003">
<title>Public&#x2013;private partnership practices of the BRICS countries and best practice</title>
<p>Best practice refers to:</p>
<disp-quote>
<p>[&#x2026; <italic>A</italic>] working method or set of working methods that is officially accepted as being the best to use in a particular business or industry, usually described formally and in detail. (Cambridge University Press <xref ref-type="bibr" rid="CIT0010">2017</xref>)</p>
</disp-quote>
<p>For PPPs, best practice includes the establishment of a legal framework for the regulation of PPPs to strengthen investor confidence (International Bank for Reconstruction and Development/The World Bank [IBRD/WB] <xref ref-type="bibr" rid="CIT0028">2017</xref>; Tiong <xref ref-type="bibr" rid="CIT0072">2013</xref>). By contrasting the regulations of PPPs in the BRICS countries, it is revealed that all of these countries have established legal frameworks for PPPs, albeit at differing levels of maturity (Churakov <xref ref-type="bibr" rid="CIT0012">2014</xref>; Ittmann <xref ref-type="bibr" rid="CIT0031">2017</xref>; Meng et al. <xref ref-type="bibr" rid="CIT0045">2015</xref>; Pereira <xref ref-type="bibr" rid="CIT0053">2014</xref>; Telang &#x0026; Kutumbale <xref ref-type="bibr" rid="CIT0066">2014</xref>). Brazil and Russia appear to be the only BRICS countries with specific legislation for PPPs (Churakov <xref ref-type="bibr" rid="CIT0012">2014</xref>; Pereira <xref ref-type="bibr" rid="CIT0053">2014</xref>). No specific legislation and regulations exist for PPPs in India according to Telang and Kutumbale (<xref ref-type="bibr" rid="CIT0066">2014</xref>). Public&#x2013;private partnerships appear to be regulated through other administrative and commercial laws and regulations of the country (Telang &#x0026; Kutumbale <xref ref-type="bibr" rid="CIT0066">2014</xref>). Meng et al. (<xref ref-type="bibr" rid="CIT0045">2015</xref>) also show that China does not have any specific law that governs PPPs. It regulates PPPs through the <italic>Administrative Measures on Concession of Infrastructure and Public Utilities Projects</italic>, which were adopted in 2015. Similarly, South Africa does not have a specific law that governs PPPs. The country has made provision within its <italic>Public Finance Management Act</italic> No. 1 of 1999 (PFMA) and <italic>Treasury Regulation 16</italic> for the regulation of PPPs undertaken at the national and provincial tiers of government. There is further provision for the regulation of PPPs undertaken at the municipal tier, using the <italic>Municipal Finance Management Act</italic> No. 56 of 2003 and its regulations and the <italic>Municipal Systems Act</italic> No. 32 of 2003 (Ittmann <xref ref-type="bibr" rid="CIT0031">2017</xref>; National Treasury <xref ref-type="bibr" rid="CIT0049">2017</xref>). It was not apparent in the literature whether or not a specific law for PPPs was required in South Africa or if it would add any value to the current regulatory framework for PPPs (Ittmann <xref ref-type="bibr" rid="CIT0031">2017</xref>; National Treasury <xref ref-type="bibr" rid="CIT0049">2017</xref>), which presents a gap in the literature.</p>
<p>Despite the lack of specific legislation for PPPs in India and China, these two countries have been able to implement the most transport PPPs amongst the BRICS countries, which indicates that a specific law in itself is not a prerequisite to the success of PPPs but rather the quality or substance of the legal framework that governs them. In this vein, the lack of specific legislation suggests that South Africa is implementing best practices when compared with these developing countries; however, an in-depth comparative study of the legal frameworks of India, China and South Africa is required to identify whether substantial similarities and differences exist in these frameworks in order to substantiate this determination.</p>
<p>Best practices also advocate for strong political support and commitment for PPPs (IBRD/WB <xref ref-type="bibr" rid="CIT0028">2017</xref>; Tiong <xref ref-type="bibr" rid="CIT0072">2013</xref>). Literature indicates that strong political support exists for PPPs in the four largest developing economies (Churakov <xref ref-type="bibr" rid="CIT0012">2014</xref>; Gopalkrishna &#x0026; Karnam <xref ref-type="bibr" rid="CIT0021">2015</xref>; Mouraviev &#x0026; Kakabadse <xref ref-type="bibr" rid="CIT0046">2014</xref>; Tiong <xref ref-type="bibr" rid="CIT0072">2013</xref>). This is demonstrated in part by several projects approved by the authorities, coupled with the allocation of adequate resources for the implementation of PPPs in their respective countries (Churakov <xref ref-type="bibr" rid="CIT0012">2014</xref>; Gopalkrishna &#x0026; Karnam <xref ref-type="bibr" rid="CIT0021">2015</xref>; Mouraviev &#x0026; Kakabadse <xref ref-type="bibr" rid="CIT0046">2014</xref>; Tiong <xref ref-type="bibr" rid="CIT0072">2013</xref>). However, in South Africa, strong political support for PPPs is not evident as, despite occasional statements from ministers and the President, these are not translated into actionable policy or legislation and the statements therefore often lack the backing to convert them into actionable projects (Aigbavboa, Liphadzi &#x0026; Thwala <xref ref-type="bibr" rid="CIT0002">2014</xref>; Ittmann <xref ref-type="bibr" rid="CIT0031">2017</xref>), which presents a gap.</p>
<p>The literature indicates that PPPs have only attained popularity over the past few years in the BRICS countries, and, as a result, the legislatures of these countries do not have the depth of knowledge and competencies required to provide effective oversight over PPP projects (Churakov <xref ref-type="bibr" rid="CIT0012">2014</xref>; Meng et al. <xref ref-type="bibr" rid="CIT0045">2015</xref>; Pereira <xref ref-type="bibr" rid="CIT0053">2014</xref>). It appears that transparency of processes and proactive disclosure of project information is still a challenge across most of the BRICS countries (Churakov <xref ref-type="bibr" rid="CIT0012">2014</xref>; Ittmann <xref ref-type="bibr" rid="CIT0031">2017</xref>; Lodge et al. <xref ref-type="bibr" rid="CIT0037">2017</xref>; Meng et al. <xref ref-type="bibr" rid="CIT0045">2015</xref>; Pereira <xref ref-type="bibr" rid="CIT0053">2014</xref>; Telang &#x0026; Kutumbale <xref ref-type="bibr" rid="CIT0066">2014</xref>). This is demonstrated in South Africa by the lack of proactive disclosure of project information (IBRD/WB <xref ref-type="bibr" rid="CIT0027">2014</xref>). In the instance of Brazil, although transparency is a key principle and legal requirement in the bid solicitation process (Pereira <xref ref-type="bibr" rid="CIT0053">2014</xref>), Lodge et al. (<xref ref-type="bibr" rid="CIT0037">2017</xref>) showed that there are transparency issues, as demonstrated by the lack of transparency in the handling of large procurements and concession design and procedures.</p>
<p>Excluding Brazil, it is unclear if there is extensive public participation and consultation in the other BRICS countries to promote the public interest (Churakov <xref ref-type="bibr" rid="CIT0012">2014</xref>; Ittmann <xref ref-type="bibr" rid="CIT0031">2017</xref>; Meng et al. <xref ref-type="bibr" rid="CIT0045">2015</xref>; Pereira <xref ref-type="bibr" rid="CIT0053">2014</xref>; Telang &#x0026; Kutumbale <xref ref-type="bibr" rid="CIT0066">2014</xref>). South Africa does not seem to be conducting extensive public participation and consultation to promote interest amongst the public (Aigbavboa et al. <xref ref-type="bibr" rid="CIT0002">2014</xref>). The literature also indicates that, with the exception of South Africa, there seems to be cooperative decision-making and trust between the public and private sectors of the other BRICS countries (Churakov <xref ref-type="bibr" rid="CIT0012">2014</xref>; Ittmann <xref ref-type="bibr" rid="CIT0031">2017</xref>; Meng et al. <xref ref-type="bibr" rid="CIT0045">2015</xref>; Pereira <xref ref-type="bibr" rid="CIT0053">2014</xref>; Telang &#x0026; Kutumbale <xref ref-type="bibr" rid="CIT0066">2014</xref>).</p>
<p>Best practices endorse the institutionalisation of PPPs, through the establishment of PPP units at either a national or subnational level (Ittmann <xref ref-type="bibr" rid="CIT0031">2017</xref>; Perera <xref ref-type="bibr" rid="CIT0054">2016</xref>; Polyakova &#x0026; Vasilyeva <xref ref-type="bibr" rid="CIT0055">2016</xref>). The literature indicates that all the BRICS countries have PPP units and that all these units have clearly defined institutional responsibilities and arrangements (IBRD/WB <xref ref-type="bibr" rid="CIT0027">2014</xref>; Istrate &#x0026; Puentes <xref ref-type="bibr" rid="CIT0030">2011</xref>). All the BRICS countries have established these units at the national level of their respective governments (Istrate &#x0026; Puentes <xref ref-type="bibr" rid="CIT0030">2011</xref>). However, there is growing recognition for a need to establish similar units or agencies at the subnational level to improve access to technical competencies at the lower levels of government (Istrate &#x0026; Puentes <xref ref-type="bibr" rid="CIT0030">2011</xref>).</p>
<p>The adoption of a coherent process that will assist in the identification, selection and assessment of high-quality PPP projects is also prescribed by best practices (Meng et al. <xref ref-type="bibr" rid="CIT0045">2015</xref>; Telang &#x0026; Kutumbale <xref ref-type="bibr" rid="CIT0066">2014</xref>). An iterative approach in the PPP process is recommended to stop the selection of low-quality projects from being implemented and wasting resources (IBRD/WB <xref ref-type="bibr" rid="CIT0028">2017</xref>). This is achieved by breaking the process into phases and developing and appraising each phase iteratively (IBRD/WB <xref ref-type="bibr" rid="CIT0028">2017</xref>). Aspects of an iterative approach are evident in South Africa as the cycle is fragmented into phases, and approvals from the National Treasury are sought after each phase of the PPP cycle (IBRD/WB <xref ref-type="bibr" rid="CIT0028">2017</xref>). Similarly, clearance is required in India to proceed to the third phase of the cycle (Department of Economic Affairs <xref ref-type="bibr" rid="CIT0017">2010</xref>). Although aspects of an iterative review in the approval requirements of PPPs in India are evident, the high number of projects being terminated that have reached financial closure undermines the sincerity of this process (Agarchand &#x0026; Laishram <xref ref-type="bibr" rid="CIT0001">2017</xref>). It can take as much as 24&#x2013;36 months to satisfy all the conditions of the project and financing agreements required to reach financial closure (Mandri-Perrott <xref ref-type="bibr" rid="CIT0041">n.d.</xref>), making cancellations at this advanced stage unlikely. Cancellations are typically expected at the pre-feasibility or feasibility stages, as decision-makers would have already had an idea of whether or not to proceed with the said projects, instead of waiting such a long time only to cancel (Beerbohm &#x0026; Fitzgerald <xref ref-type="bibr" rid="CIT0008">2019</xref>).</p>
<p>The literature advocates for the selection of PPPs with a large project size (IBRD/WB <xref ref-type="bibr" rid="CIT0028">2017</xref>; Tiong <xref ref-type="bibr" rid="CIT0072">2013</xref>). A large project size refers to PPPs with a high cost, which Tiong (<xref ref-type="bibr" rid="CIT0072">2013</xref>) suggested should be equal or greater than USD50 bn. This is evident in the BRICS countries that have a high threshold for PPP project size (Churakov <xref ref-type="bibr" rid="CIT0012">2014</xref>; Meng et al. <xref ref-type="bibr" rid="CIT0045">2015</xref>; National Treasury <xref ref-type="bibr" rid="CIT0049">2017</xref>; Pereira <xref ref-type="bibr" rid="CIT0053">2014</xref>; Telang &#x0026; Kutumbale <xref ref-type="bibr" rid="CIT0066">2014</xref>). The literature further advocates for the selection of projects with long-term project tenure (IBRD/WB <xref ref-type="bibr" rid="CIT0028">2017</xref>; Tiong <xref ref-type="bibr" rid="CIT0072">2013</xref>). Long-term contracts span a period between 11 and 30 years (Churakov <xref ref-type="bibr" rid="CIT0012">2014</xref>; Meng et al. <xref ref-type="bibr" rid="CIT0045">2015</xref>; Pereira <xref ref-type="bibr" rid="CIT0053">2014</xref>; Telang &#x0026; Kutumbale <xref ref-type="bibr" rid="CIT0066">2014</xref>). Most of the BRICS countries appear to prioritise long-term PPP projects (Churakov <xref ref-type="bibr" rid="CIT0012">2014</xref>; Meng et al. <xref ref-type="bibr" rid="CIT0045">2015</xref>; National Treasury <xref ref-type="bibr" rid="CIT0049">2017</xref>; Pereira <xref ref-type="bibr" rid="CIT0053">2014</xref>; Telang &#x0026; Kutumbale <xref ref-type="bibr" rid="CIT0066">2014</xref>). All the BRICS countries involve the preparation and approval of a viable business case as a part of the approval process for implementing PPPs (Churakov <xref ref-type="bibr" rid="CIT0012">2014</xref>; Ittmann <xref ref-type="bibr" rid="CIT0031">2017</xref>; Meng et al. <xref ref-type="bibr" rid="CIT0045">2015</xref>; National Treasury <xref ref-type="bibr" rid="CIT0049">2017</xref>; Pereira <xref ref-type="bibr" rid="CIT0053">2014</xref>; Telang &#x0026; Kutumbale <xref ref-type="bibr" rid="CIT0066">2014</xref>). However, India seems to be experiencing a challenge relating to the approval of several business cases, which have later been found not to have been viable (Telang &#x0026; Kutumbale <xref ref-type="bibr" rid="CIT0066">2014</xref>).</p>
<p>Literature reveals several risks that can adversely affect PPPs (Global Infrastructure Hub <xref ref-type="bibr" rid="CIT0020">2016</xref>; Taruvinga <xref ref-type="bibr" rid="CIT0065">2017</xref>). These risks include site risk, design, construction and commissioning risk, operations risk, demand and other commercial risks, regulatory or political risk, change in the legal framework, default risk, economic or financial risk, force majeure and asset ownership (Global Infrastructure Hub <xref ref-type="bibr" rid="CIT0020">2016</xref>; Taruvinga <xref ref-type="bibr" rid="CIT0065">2017</xref>). Risk can also emanate from other sources, which include the availability of labour and raw materials, contract variation, the environment, a faulty tender specification, ground conditions, insolvency of subcontractors and suppliers, the lack of commitment from a partner, the lack of experience in the PPP environment, land expropriation, residual risk and unproven engineering technologies (Taruvinga <xref ref-type="bibr" rid="CIT0065">2017</xref>).</p>
<p>The various types of risks can have a different impact on a project, such as delays, cost overruns or even project failure. For example, Australia has some poor examples of transport PPPs, such as the Sydney Light Rail PPP, where the project cost increased from USD1.6 bn to USD2.77 bn because of a law suit against the government for failing to disclose key information that had a bearing on the project (Gilbert and Tobin <xref ref-type="bibr" rid="CIT0019">2020</xref>). The Cross River Rail PPP in Queensland is another example of a poor PPP that is experiencing significant cost overruns because of design flaws (Gilbert and Tobin <xref ref-type="bibr" rid="CIT0019">2020</xref>).</p>
<p>To address this problem, best practices prescribe the adoption of a coherent process for the allocation of risk (Meng et al. <xref ref-type="bibr" rid="CIT0045">2015</xref>; Telang &#x0026; Kutumbale <xref ref-type="bibr" rid="CIT0066">2014</xref>). The literature outlines some principles for allocating risk such as, firstly, risk should preferably be allocated before the start of a project (Taruvinga <xref ref-type="bibr" rid="CIT0065">2017</xref>). Secondly, it should be allocated to the party best able to control the likelihood of the risk occurring (Taruvinga <xref ref-type="bibr" rid="CIT0065">2017</xref>). For example, the private party typically bears the technical expertise required for construction; therefore, any delays relating to construction should be carried by this party (Taruvinga <xref ref-type="bibr" rid="CIT0065">2017</xref>). Thirdly, the party best able to control the impact of the risk on project outcomes should also be considered when allocating risk (Cruz, Marques &#x0026; Franco <xref ref-type="bibr" rid="CIT0013">2015</xref>). For instance, the private party can mitigate the risk posed by earthquakes to a construction project through the use of innovation, design and technology (Cruz et al. <xref ref-type="bibr" rid="CIT0013">2015</xref>). Fourthly, risk should be allocated to the party that can absorb it at the lowest cost, if the likelihood and impact cannot be controlled (Tiong <xref ref-type="bibr" rid="CIT0072">2013</xref>). Typically, governments can absorb risk better than private parties, as they can spread risk to several taxpayers compared with the private party, which would have to spread their risk to a few shareholders (Tiong <xref ref-type="bibr" rid="CIT0072">2013</xref>).</p>
<p>It appears that all the BRICS countries typically allocate risk to the party best suited to deal with it (Churakov <xref ref-type="bibr" rid="CIT0012">2014</xref>; Meng et al. <xref ref-type="bibr" rid="CIT0045">2015</xref>; National Treasury <xref ref-type="bibr" rid="CIT0049">2017</xref>; Pereira <xref ref-type="bibr" rid="CIT0053">2014</xref>; Telang &#x0026; Kutumbale <xref ref-type="bibr" rid="CIT0066">2014</xref>). In all these countries, there seems to be an adequate transfer of risk to the private party (Churakov <xref ref-type="bibr" rid="CIT0012">2014</xref>; Meng et al. <xref ref-type="bibr" rid="CIT0045">2015</xref>; National Treasury <xref ref-type="bibr" rid="CIT0049">2017</xref>; Pereira <xref ref-type="bibr" rid="CIT0053">2014</xref>; Telang &#x0026; Kutumbale <xref ref-type="bibr" rid="CIT0066">2014</xref>). However, in specific cases, the public sector seems to carry most of the risk, as is demonstrated by the Gautrain Rapid Rail project in South Africa, where the public sector carries most of the financial risk (Dachs <xref ref-type="bibr" rid="CIT0014">2011</xref>; National Treasury <xref ref-type="bibr" rid="CIT0049">2017</xref>).</p>
<p>Best practices also recommend the development of appropriate instruments for the financing of PPP projects (Ittmann <xref ref-type="bibr" rid="CIT0031">2017</xref>; Tiong <xref ref-type="bibr" rid="CIT0072">2013</xref>). This includes developing long-term financing instruments to allow payments for PPPs to become affordable (IBRD/WB <xref ref-type="bibr" rid="CIT0028">2017</xref>). Except for South Africa, the BRICS countries have well-established long-term financing instruments (Beck, Maimbo, Faye &#x0026; Triki <xref ref-type="bibr" rid="CIT0007">2011</xref>; Churakov <xref ref-type="bibr" rid="CIT0012">2014</xref>; Meng et al. <xref ref-type="bibr" rid="CIT0045">2015</xref>; Pereira <xref ref-type="bibr" rid="CIT0053">2014</xref>; Telang &#x0026; Kutumbale <xref ref-type="bibr" rid="CIT0066">2014</xref>). Project bond financing is an example of a long-term financing instrument (Deloitte <xref ref-type="bibr" rid="CIT0015">2018</xref>). It is not prevalent in South Africa, as is demonstrated by the limited investment-grade listings on the Johannesburg Stock Exchange; however, it is expected to play a greater role in the future (Deloitte <xref ref-type="bibr" rid="CIT0015">2018</xref>).</p>
<p>Tiong (<xref ref-type="bibr" rid="CIT0072">2013</xref>) also prescribed the establishment of regional rating agencies as part of a country&#x2019;s strategy to promote PPPs. China, Russia and India have established regional rating agencies (Tiong <xref ref-type="bibr" rid="CIT0072">2013</xref>). Although Brazil and South Africa do not have regional rating agencies, they do have international credit rating agencies represented within their borders (Tiong <xref ref-type="bibr" rid="CIT0072">2013</xref>). The Africa Report (<xref ref-type="bibr" rid="CIT0067">2014</xref>) shows the establishment of a domestic credit rating agency is important for the growth of Africa&#x2019;s capital markets and investment in the continent. Such an agency could provide alternative, in-depth analysis into &#x2018;transactions and balance-sheet activities of entities across the region&#x2019; (Africa Report <xref ref-type="bibr" rid="CIT0067">2014</xref>: para. 1). By providing better information on entities operating within the region, the fears of investors could be allayed (Africa Report <xref ref-type="bibr" rid="CIT0067">2014</xref>).</p>
<p>The creation of a competitive environment for PPP projects is encouraged by best practice (Ittmann <xref ref-type="bibr" rid="CIT0031">2017</xref>; Tiong <xref ref-type="bibr" rid="CIT0072">2013</xref>). The literature indicates that competition in the PPP market is encouraged across all the BRICS countries, albeit at differing levels (Churakov <xref ref-type="bibr" rid="CIT0012">2014</xref>; Lukmanova &#x0026; Mishlanova <xref ref-type="bibr" rid="CIT0038">2015</xref>; Meng et al. <xref ref-type="bibr" rid="CIT0045">2015</xref>; National Treasury <xref ref-type="bibr" rid="CIT0049">2017</xref>; Pereira <xref ref-type="bibr" rid="CIT0053">2014</xref>; Telang &#x0026; Kutumbale <xref ref-type="bibr" rid="CIT0066">2014</xref>). It suggests that there is robust competition in their PPP markets (Churakov <xref ref-type="bibr" rid="CIT0012">2014</xref>; Meng et al. <xref ref-type="bibr" rid="CIT0045">2015</xref>; Pereira <xref ref-type="bibr" rid="CIT0053">2014</xref>; Telang &#x0026; Kutumbale <xref ref-type="bibr" rid="CIT0066">2014</xref>). This is an important aspect, as according to Meng et al. (<xref ref-type="bibr" rid="CIT0045">2015</xref>), competition drives efficiencies within the PPP market. All the BRICS countries have measures to deal with unsolicited proposals and intellectual property (Churakov <xref ref-type="bibr" rid="CIT0012">2014</xref>; Lukmanova &#x0026; Mishlanova <xref ref-type="bibr" rid="CIT0038">2015</xref>; Meng et al. <xref ref-type="bibr" rid="CIT0045">2015</xref>; National Treasury <xref ref-type="bibr" rid="CIT0049">2017</xref>; Pereira <xref ref-type="bibr" rid="CIT0053">2014</xref>; Telang &#x0026; Kutumbale <xref ref-type="bibr" rid="CIT0066">2014</xref>; Thieriot &#x0026; Dominguez <xref ref-type="bibr" rid="CIT0069">2015</xref>). Although South Africa&#x2019;s regulatory framework allows for unsolicited proposals, it seems as though there is reluctance to approve projects through this form of procurement, as it is not deemed to be cost effective (National Treasury <xref ref-type="bibr" rid="CIT0049">2017</xref>).</p>
<p>Best practices recommend outlining a coherent procedure for the management of the transaction process of PPP projects (Bloomfield &#x0026; Ahern <xref ref-type="bibr" rid="CIT0009">2011</xref>; IBRD/WB <xref ref-type="bibr" rid="CIT0027">2014</xref>; Iossa &#x0026; Martimort <xref ref-type="bibr" rid="CIT0029">2012</xref>). The appointment of transaction advisors is a common commercial practice in all the BRICS countries (Bloomfield &#x0026; Ahern <xref ref-type="bibr" rid="CIT0009">2011</xref>; IBRD/WB <xref ref-type="bibr" rid="CIT0027">2014</xref>; Iossa &#x0026; Martimort <xref ref-type="bibr" rid="CIT0029">2012</xref>). The bid process is managed in all these countries, although at differing levels of transparency (Bloomfield &#x0026; Ahern <xref ref-type="bibr" rid="CIT0009">2011</xref>; IBRD/WB <xref ref-type="bibr" rid="CIT0027">2014</xref>; Iossa &#x0026; Martimort <xref ref-type="bibr" rid="CIT0029">2012</xref>).</p>
<p>The PPP contract design for all the BRICS countries typically includes provision for performance and dispute resolution mechanisms, payment and adjustment mechanisms, as well as provision for the termination of the contract (Bloomfield &#x0026; Ahern <xref ref-type="bibr" rid="CIT0009">2011</xref>; Dachs <xref ref-type="bibr" rid="CIT0014">2011</xref>; IBRD/WB <xref ref-type="bibr" rid="CIT0027">2014</xref>; Istrate &#x0026; Puentes <xref ref-type="bibr" rid="CIT0030">2011</xref>; Tiong <xref ref-type="bibr" rid="CIT0072">2013</xref>). Best practices also prescribe outlining a coherent procedure for the management of the PPP contract (Chartered Institute of Procurement and Supply <xref ref-type="bibr" rid="CIT0011">n.d.</xref>). The literature shows that the practice of establishing contract management structures is recognised in all the BRICS countries by contracting authorities (Dachs <xref ref-type="bibr" rid="CIT0014">2011</xref>; IBRD/WB <xref ref-type="bibr" rid="CIT0027">2014</xref>; Istrate &#x0026; Puentes <xref ref-type="bibr" rid="CIT0030">2011</xref>; Johnston &#x0026; Kouzmin <xref ref-type="bibr" rid="CIT0032">2010</xref>; Tiong <xref ref-type="bibr" rid="CIT0072">2013</xref>). It is not apparent whether there is adequate monitoring and evaluation of performance in all the BRICS countries, which presents a research gap (Dachs <xref ref-type="bibr" rid="CIT0014">2011</xref>; IBRD/WB <xref ref-type="bibr" rid="CIT0027">2014</xref>; Istrate &#x0026; Puentes <xref ref-type="bibr" rid="CIT0030">2011</xref>; Johnston &#x0026; Kouzmin <xref ref-type="bibr" rid="CIT0032">2010</xref>; Tiong <xref ref-type="bibr" rid="CIT0072">2013</xref>). The expiry of the contract and procedures for the handover of the asset are specified in the PPP contracts of all the BRICS countries (Dachs <xref ref-type="bibr" rid="CIT0014">2011</xref>; IBRD/WB <xref ref-type="bibr" rid="CIT0027">2014</xref>; Istrate &#x0026; Puentes <xref ref-type="bibr" rid="CIT0030">2011</xref>; Johnston &#x0026; Kouzmin <xref ref-type="bibr" rid="CIT0032">2010</xref>; Tiong <xref ref-type="bibr" rid="CIT0072">2013</xref>). Given that no contract can ever be truly regarded as being complete, best practice prescribes outlining a strategy to deal with an incomplete contract (Mansor &#x0026; Rashid <xref ref-type="bibr" rid="CIT0042">2016</xref>). In this regard, South Africa and India standardise their contracts to deal with issues emanating from an incomplete contract (Mansor &#x0026; Rashid <xref ref-type="bibr" rid="CIT0042">2016</xref>). This is on the basis that standardisation prescribes the fundamental elements that need to be incorporated into any contract for it to be regarded as nearly complete as possible.</p>
<p>In light of the given discussion, <xref ref-type="table" rid="T0001">Table 1</xref> displays the level of conformity of the BRICS countries to best practice. It reveals that the key areas where South Africa&#x2019;s practices diverge from the other BRICS countries are the lack of strong political commitment and support, cooperative decision-making and trust, appropriate skills transfer and capacity development of public officials, and the establishment and identification of long-term financing instruments.</p>
<table-wrap id="T0001">
<label>TABLE 1</label>
<caption><p>Conformity of the BRICS countries to best practices.</p></caption>
<table frame="hsides" rules="groups">
<thead>
<tr>
<th valign="top" align="left">Best practice</th>
<th valign="top" align="center">Brazil</th>
<th valign="top" align="center">Russia</th>
<th valign="top" align="center">India</th>
<th valign="top" align="center">China</th>
<th valign="top" align="center">South Africa</th>
</tr>
</thead>
<tbody>
<tr>
<td align="left">1. Establishment of a legal framework for PPP</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
</tr>
<tr>
<td align="left">2. Specific PPP legislation</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="left"></td>
<td align="left"></td>
<td align="center"></td>
</tr>
<tr>
<td align="left">3. Strong political commitment and support</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="left"></td>
</tr>
<tr>
<td align="left">4. Effective oversight by the legislature</td>
<td align="left"></td>
<td align="left"></td>
<td align="left"></td>
<td align="left"></td>
<td align="left"></td>
</tr>
<tr>
<td align="left">5. Transparency of processes and proactive disclosure of project information</td>
<td align="left"></td>
<td align="left"></td>
<td align="left"></td>
<td align="left"></td>
<td align="left"></td>
</tr>
<tr>
<td align="left">6. Extensive public participation and consultation to promote public interest</td>
<td align="center">&#x221A;</td>
<td align="left"></td>
<td align="left"></td>
<td align="left"></td>
<td align="left"></td>
</tr>
<tr>
<td align="left">7. Cooperative decision-making and trust</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center"></td>
</tr>
<tr>
<td align="left">8. Clear definition of institutional responsibilities and arrangements</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
</tr>
<tr>
<td align="left">9. Appropriate skills transfer and capacity development of public officials</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="left"></td>
</tr>
<tr>
<td align="left">10. Establishment of dedicated PPP units at national and subnational levels</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
</tr>
<tr>
<td align="left">11. Appropriate project selection and pre-assessment</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="left"></td>
<td align="center">&#x221A;</td>
<td align="left"></td>
</tr>
<tr>
<td align="left">12. An iterative approach to the screening of projects</td>
<td align="left"></td>
<td align="left"></td>
<td align="left"></td>
<td align="left"></td>
<td align="left"></td>
</tr>
<tr>
<td align="left">13. High threshold for project cost</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
</tr>
<tr>
<td align="left">14. Prioritisation of long-term projects</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
</tr>
<tr>
<td align="left">15. Preparation and approval of a viable business case</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="left"></td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
</tr>
<tr>
<td align="left">16. Allocation of risk to the party best suited to deal with it</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
</tr>
<tr>
<td align="left">17. Adequate transfer of risk to the private partner</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
</tr>
<tr>
<td align="left">18. Establishment and identification of long-term financing instruments</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="left"></td>
</tr>
<tr>
<td align="left">19. Establishment of a regional credit rating agency that provides investors with information on positive and negative situations in the economy.</td>
<td align="center"></td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="left"></td>
</tr>
<tr>
<td align="left">20. Promotion of competition in the market</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
</tr>
<tr>
<td align="left">21. Measures for dealing with unsolicited proposals and intellectual property</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
</tr>
<tr>
<td align="left">22. Appointment of transaction advisors</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
</tr>
<tr>
<td align="left">23. Management of the bid process</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
</tr>
<tr>
<td align="left">24. Performance</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
</tr>
<tr>
<td align="left">25. Dispute resolution</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
</tr>
<tr>
<td align="left">26. Specification of payment and adjustment mechanisms</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
</tr>
<tr>
<td align="left">27. Provision for contract termination</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
</tr>
<tr>
<td align="left">28. Establishment of contract management structures</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
</tr>
<tr>
<td align="left">29. Adequate monitoring and evaluation of performance</td>
<td align="left"></td>
<td align="left"></td>
<td align="left"></td>
<td align="left"></td>
<td align="left"></td>
</tr>
<tr>
<td align="left">30. Expiry of the contract and handover of the asset</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
<td align="center">&#x221A;</td>
</tr>
<tr>
<td align="left">31. Standardisation of contracts</td>
<td align="center"></td>
<td align="center"></td>
<td align="center">&#x221A;</td>
<td align="center"></td>
<td align="center">&#x221A;</td>
</tr>
<tr>
<td align="left" colspan="6"><hr/></td>
</tr>
<tr>
<td align="left"><bold>Total</bold></td>
<td align="center"><bold>26</bold></td>
<td align="center"><bold>25</bold></td>
<td align="center"><bold>23</bold></td>
<td align="center"><bold>24</bold></td>
<td align="center"><bold>19</bold></td>
</tr>
</tbody>
</table>
<table-wrap-foot>
<fn><p>PPP, public&#x2013;private partnership; BRICS, Brazil, Russia, India, China and South Africa.</p></fn>
</table-wrap-foot>
</table-wrap>
<p>Despite having a significantly greater number of transport PPPs, the levels of conformity to best practice in India and China are comparable to Brazil and Russia, as shown in <xref ref-type="table" rid="T0001">Table 1</xref>. This suggests that there might be substantial differences in the manner in which the listed practices are implemented, which are contributing to a greater uptake of transport PPPs in India and China.</p>
</sec>
</sec>
<sec id="s0004">
<title>Research method and design</title>
<p>The aim of the study was to describe the problems faced in the South African PPP process, firstly by comparing and contrasting PPP practices of South Africa with its BRICS counterparts in view of understanding the reasons for the low uptake of transport PPPs in the country, and secondly, by interviewing transport PPP experts on their opinions on constraints and possible solutions to PPPs in the country. To achieve this aim, the research design and plan was descriptive and exploratory, and the methodological choice was qualitative research. Qualitative research was the most appropriate method, as there is limited research and experience in South Africa on transport PPPs, which presented some difficulty in collecting meaningful quantitative data. Secondary and primary data were collected and analysed, as both were required to address the research objectives. Secondary data were obtained from the World Bank&#x2019;s Private Participation in Infrastructure Database (WBG <xref ref-type="bibr" rid="CIT0080">2019</xref>) and the PPP database of the GTAC (<xref ref-type="bibr" rid="CIT0024">2019</xref>). Primary data were collected through interviews at the participants&#x2019; preferred venues, using semistructured interview guides. As the size of the population was unknown, a sampling frame was compiled through the amalgamation of data on organisations involved in transport PPPs. This information was found in the above-mentioned databases and supplemented by an Internet search.</p>
<p>A sample of fourteen participants was selected from this sampling frame to participate using purposive sampling. Saunders, Lewis and Thornhill (<xref ref-type="bibr" rid="CIT0061">2009</xref>) stated that a small sample is ideal as data saturation is likely to be realised after the 12th in-depth interview. Data saturation refers to a point where the additional data being provided by participants becomes redundant, with no new information or insights provided (Macnee &#x0026; McCabe <xref ref-type="bibr" rid="CIT0039">2008</xref>). Successive participants were interviewed until no new themes emerged (Macnee &#x0026; McCabe <xref ref-type="bibr" rid="CIT0039">2008</xref>), and data saturation was considered to have been achieved. The procedure used for the interviews was face to face. It entailed the following: the preparation and pretesting of interview questions; approaching and requesting the participation of participants; the introduction of the interview; indicating the length of the interview; the assurance of confidentiality; recording the interview; and closing the interview (Food and Agriculture Organisation of the United Nations <xref ref-type="bibr" rid="CIT0018">2019</xref>). The transcribed interviews were then amalgamated using Microsoft Word and uploaded to ATLAS.ti for coding and development of themes. The findings were then analysed and described and conclusions drawn.</p>
</sec>
<sec id="s0005">
<title>Findings and discussion</title>
<p>This section provides the results of the study that address the specific objectives and a discussion to reveal new insights. Section &#x2018;Trends in the Public&#x2013;Private Partnership practices of the BRICS countries&#x2019; presents results from the secondary data analysis, and Section &#x2018;Transport industry players&#x2019; perspectives&#x2019; presents the results from the interview process.</p>
<sec id="s20006">
<title>Trends in the public&#x2013;private partnership practices of the BRICS countries</title>
<p>The secondary data findings reveal that transport PPPs in the BRICS countries mainly involve brownfield projects, which are used to transfer the responsibility for upgrading and managing existing assets to private parties (Pan <xref ref-type="bibr" rid="CIT0052">n.d.</xref>). Brownfield projects are ideal for PPPs because they can take longer to develop and carry greater risk than greenfield projects (Gray <xref ref-type="bibr" rid="CIT0025">n.d.</xref>). These aspects provide an opportunity for long-term contracts that afford stability and predictability (Tan &#x0026; Zhao <xref ref-type="bibr" rid="CIT0064">2019</xref>) and the ability of the private party to benefit by charging a premium for most of the risk transferred to it (Marquaire <xref ref-type="bibr" rid="CIT0043">2020</xref>).</p>
<p>The findings also show that the transport PPPs of the BRICS countries are predominately in the road sector, entailing the building, rehabilitating, operation and transfer of highways. This finding is confirmed by Rehman (<xref ref-type="bibr" rid="CIT0058">2013</xref>) and Sanghai (<xref ref-type="bibr" rid="CIT0059">2021</xref>), who showed that long-term finance for PPP projects is not readily available for project companies in India intending to develop greenfield infrastructure projects, which are new developments that have greater flexibility to introduce new technologies and ideas without concern for existing technologies, infrastructure and systems found in brownfield projects (Pan <xref ref-type="bibr" rid="CIT0052">n.d.</xref>). The typical sources of long-term finance, such as insurance companies and pension funds, do not finance these types of projects (Rehman <xref ref-type="bibr" rid="CIT0058">2013</xref>). Therefore, the lack of long-term finance for greenfield projects would discourage investment in this type of project in this country. However, China contradicts this finding, as it has a greater affinity for greenfield projects. This finding is evidenced by Thieriot and Dominguez (<xref ref-type="bibr" rid="CIT0069">2015</xref>), who stated that in China &#x2018;greenfield projects represent a majority of the private participation in infrastructure, mostly through build&#x2013;operate&#x2013;transfer agreements&#x2019;. The prevalence of road projects is verified by Palmer (<xref ref-type="bibr" rid="CIT0051">2015</xref>) and Wheat et al. (<xref ref-type="bibr" rid="CIT0075">2019</xref>), who show that there is a greater demand for road projects compared with other modes, such as rail, which is attributed to lower traffic risk and greater affordability (Wheat et al. <xref ref-type="bibr" rid="CIT0075">2019</xref>; Withrington <xref ref-type="bibr" rid="CIT0076">2011</xref>).</p>
<p>The findings also reveal a trend for the establishment of legal frameworks in each of the BRICS countries, which are characterised by the autonomy of different tiers of government to enter into a contract, as is evidenced by Churakov (<xref ref-type="bibr" rid="CIT0012">2014</xref>), Pereira (<xref ref-type="bibr" rid="CIT0053">2014</xref>), Telang and Kutumbale (<xref ref-type="bibr" rid="CIT0066">2014</xref>), Meng et al. (<xref ref-type="bibr" rid="CIT0045">2015</xref>) and Ittmann (<xref ref-type="bibr" rid="CIT0031">2017</xref>). The literature also reveals that Brazil (Pereira <xref ref-type="bibr" rid="CIT0053">2014</xref>), South Africa (Ittmann <xref ref-type="bibr" rid="CIT0031">2017</xref>) and Russia (Polyakova &#x0026; Vasilyeva <xref ref-type="bibr" rid="CIT0055">2016</xref>) have the authority to grant contracts across different levels of government. For these countries, the granting of contracts is predominantly realised at the national as well as the provincial tiers (Public Private Infrastructure Advisory Facility <xref ref-type="bibr" rid="CIT0056">2017</xref>). This trend is attributed to the establishment of PPP units, which are recognised for their contribution to the development of contracting capacity, at the higher echelons of governments of these countries (Istrate &#x0026; Puentes <xref ref-type="bibr" rid="CIT0030">2011</xref>). As a result, there is greater capacity to contract at these tiers of government.</p>
<p>What was not expected was China&#x2019;s contradiction of this trend, as the data show that this country realised the greatest uptake of contracts at the municipal or local level of its government, despite having located its PPP unit at the national tier. This finding is confirmed by Guo, Martek and Chuan (<xref ref-type="bibr" rid="CIT0026">2019</xref>:2), who indicated that &#x2018;more than 90&#x0025; of PPP projects were initiated by local governments in China&#x2019;. The prevalence of PPPs at the local level is attributed to the introduction of a policy titled &#x2018;Opinions on strengthening the management of local government debt&#x2019;, which allowed for meaningful private sector participation in urban infrastructure through franchise and other options (Guo et al. <xref ref-type="bibr" rid="CIT0026">2019</xref>).</p>
<p><xref ref-type="fig" rid="F0002">Figure 2</xref> displays the frequency distribution of data categorised under a government granting contract. Of these countries, India granted the most contracts, followed by China, Brazil, Russia and then South Africa. Between them, the Asian economies of India and China accounted for most of the contracts. Further inspection also indicates that most of these countries have granted contracts across all three levels of their respective governments (i.e. national, state or provincial and local or municipal). The exception is South Africa, which has not granted any contract at the municipal or local level (National Treasury <xref ref-type="bibr" rid="CIT0049">2017</xref>). It has only granted one contract at the national level for the Beitbridge Border Post bridge and two contracts at the state or provincial levels for the Gautrain Rapid Rail Project and the Durban Passenger Terminal, operated by MSC Cruises (GTAC <xref ref-type="bibr" rid="CIT0024">2019</xref>; WBG <xref ref-type="bibr" rid="CIT0080">2019</xref>). It is also evident that most BRICS countries predominantly granted contracts at the national or provincial tier of their governments. The exception is China, which granted contracts mainly at the local or municipal level of its government.</p>
<fig id="F0002">
<label>FIGURE 2</label>
<caption><p>Frequency distribution of government granting contracts.</p></caption>
<graphic xmlns:xlink="http://www.w3.org/1999/xlink" xlink:href="JTSCM-16-733-g002.tif"/>
</fig>
<p>The findings also revealed that, although in some instances the BRICS governments receive unsolicited proposals, contracts are predominantly awarded through a competitive bidding process, which emanates from solicited proposals (National Treasury <xref ref-type="bibr" rid="CIT0049">2017</xref>), where less than six bids are usually received, as is evidenced by Jones and Bloomfield (<xref ref-type="bibr" rid="CIT0033">2020</xref>). For example, they indicate that although the data of the number of bidders in China has not been disclosed, the number of bidders will be low as the level of competitive tendering in China is limited by the regulations. In South Africa, competition is also prioritised as it is deemed to be cost effective (National Treasury <xref ref-type="bibr" rid="CIT0049">2017</xref>). The dominance of competitive bidding is attributed to the benefits that the public sector derives from the competition, such as value for money and innovation (Arata, Petrangeli &#x0026; Longo <xref ref-type="bibr" rid="CIT0004">2016</xref>; National Treasury <xref ref-type="bibr" rid="CIT0049">2017</xref>).</p>
<p>The most prevalent contract periods have a span of between 11 and 30 years and revenue is largely generated through user fees. The prioritisation of long-term contracts is not surprising as Barr (<xref ref-type="bibr" rid="CIT0006">2020</xref>: para. 3) stated that &#x2018;concrete roads offer an expected service life of roughly 20&#x2013;25 years, whilst asphalt roads are likely to last approximately 18 years.&#x2019; Therefore, there is a need for contracts to provide a project term that is long enough to capture key lifecycle costs and enable lenders to provide the maximum term on debt repayments (APM Group <xref ref-type="bibr" rid="CIT0003">2020</xref>). The results also show that, in some instances, the public sector supplements this revenue through fixed or variable annuity or availability payments as is evidenced by Thillai, Deep and Mangu (<xref ref-type="bibr" rid="CIT0070">2018</xref>).</p>
<p>Disclosure of PPP information is often regarded as problematic, and to this end, the World Bank, through a global review of disclosure frameworks, identified five reports that would provide a holistic approach to disclosure (WBG <xref ref-type="bibr" rid="CIT0079">2016</xref>). It indicates that literature is limited on policy and practice in PPP disclosure, and it has therefore developed these reports as part of a broad framework to address this gap (WBG <xref ref-type="bibr" rid="CIT0079">2016</xref>). The WBG (<xref ref-type="bibr" rid="CIT0077">2013</xref>) identifies these five reports as:</p>
<disp-quote>
<p>[1] [<italic>T</italic>]he disclosure of the current PPP contract (identifying any changes made since the contract was originally signed) and relevant side agreements, including government guarantees, with minimal redactions, which reflect commercially confidential information; [2] the disclosure of future stream of payments and government commitments under PPP contracts; [3] the publication of a summary which provides in plain language the most important elements of the contract and project and key information on the rationalisation of the project, selection as a PPP and procurement; [4] information regularly on the performance of the project; and [5] a process by which information is authenticated/validated. (p. 10)</p>
</disp-quote>
<p>The findings also show that the proactive disclosure of information to the public is limited, as none of the prescribed reports are readily available or published by authorities. This trend is verified by the WBG (<xref ref-type="bibr" rid="CIT0077">2013</xref>), which shows that neither Brazil, India nor South Africa made any of the five reports required for proactive public disclosure of information available to the public. In Brazil, neither performance nor audit reports are proactively disclosed, nor are summaries of the projects and contract information provided (WBG <xref ref-type="bibr" rid="CIT0077">2013</xref>). In India, performance reports are disclosed reactively, whilst summaries of project and contract information are not provided (WBG <xref ref-type="bibr" rid="CIT0077">2013</xref>). In South Africa, contract information and audit reports are disclosed reactively, as interested parties need to apply to authorities for the limited contract information using the <italic>Promotion of Access to Information Act</italic> 2 of 2000 (IBRD/WB <xref ref-type="bibr" rid="CIT0027">2014</xref>). This process does not guarantee that the required information will be received in whole or in part, and it might come at a cost (IBRD/WB <xref ref-type="bibr" rid="CIT0027">2014</xref>). Marques (<xref ref-type="bibr" rid="CIT0044">2018</xref>) attributed the lack of transparency to the perceived sensitivity of the protection of intellectual property. Some proponents of PPPs claim that this form of procurement encourages the use of new technologies that are usually proprietary to the private sector (IBRD/WB <xref ref-type="bibr" rid="CIT0028">2017</xref>). As a result, governments are reluctant to proactively disclose any contractual information that could compromise commercial secrecy and lead to costly litigation by the private sector (IBRD/WB <xref ref-type="bibr" rid="CIT0028">2017</xref>). However, Marques (<xref ref-type="bibr" rid="CIT0044">2018</xref>) indicated that this claim is seldom valid as alternatives are usually available.</p>
</sec>
<sec id="s20007">
<title>Transport industry players&#x2019; perspectives</title>
<p>To supplement the findings of the secondary data, transport experts who had experience with PPP processes in South Africa, were interviewed. <xref ref-type="table" rid="T0002">Table 2</xref> displays the profile of the interview participants. It indicates that all of the participants had more than 7 years of work experience in the transport sector and were qualified in fields related to engineering, economics and finance. Furthermore, most of the participants indicated that they held qualifications in a broad range of fields. Of the 14 participants, eight were associated with the public sector and six with the private sector. Based on their experience, the 14 participants who were chosen represented the assortment of organisations in the typical PPP structure as outlined by Delmon (<xref ref-type="bibr" rid="CIT0016">2017</xref>), which includes public authorities; special purpose vehicles; lenders; equity investors; engineering, procurement and construction contractors and subcontractors; operations and maintenance contractors; and insurers.</p>
<table-wrap id="T0002">
<label>TABLE 2</label>
<caption><p>Profile of interview participants.</p></caption>
<table frame="hsides" rules="groups">
<thead>
<tr>
<th valign="top" align="left">Participant number</th>
<th valign="top" align="left">Gender</th>
<th valign="top" align="left">Type of organisation</th>
<th valign="top" align="left">Experience in industry (years)</th>
<th valign="top" align="left">Level in organisation</th>
<th valign="top" align="left">Highest qualification</th>
<th valign="top" align="left">Study area</th>
</tr>
</thead>
<tbody>
<tr>
<td align="left">Participant 1</td>
<td align="left">Male</td>
<td align="left">State-owned engineering company</td>
<td align="left">40 years</td>
<td align="left">Senior management</td>
<td align="left">Bachelor of Science</td>
<td align="left">Civil Engineering</td>
</tr>
<tr>
<td align="left">Participant 2</td>
<td align="left">Male</td>
<td align="left">State-owned rail company</td>
<td align="left">10 years</td>
<td align="left">Senior management</td>
<td align="left">Bachelor of Commerce (Honours)</td>
<td align="left">Transport Economics</td>
</tr>
<tr>
<td align="left">Participant 3</td>
<td align="left">Male</td>
<td align="left">State-owned airport development company</td>
<td align="left">15 years</td>
<td align="left">Senior management</td>
<td align="left">Diploma</td>
<td align="left">Transport Management</td>
</tr>
<tr>
<td align="left">Participant 4</td>
<td align="left">Female</td>
<td align="left">State Department</td>
<td align="left">21 years</td>
<td align="left">Senior management</td>
<td align="left">Bachelor of Administration</td>
<td align="left">Airline Management</td>
</tr>
<tr>
<td align="left">Participant 5</td>
<td align="left">Male</td>
<td align="left">State Department</td>
<td align="left">11 years</td>
<td align="left">Senior management</td>
<td align="left">Bachelor of Administration</td>
<td align="left">Public Management</td>
</tr>
<tr>
<td align="left">Participant 6</td>
<td align="left">Male</td>
<td align="left">State-owned logistics company</td>
<td align="left">22 years</td>
<td align="left">Senior management</td>
<td align="left">Bachelor of Commerce (Honours)</td>
<td align="left">Transport Economics</td>
</tr>
<tr>
<td align="left">Participant 7</td>
<td align="left">Male</td>
<td align="left">Development Finance Institution</td>
<td align="left">9 years</td>
<td align="left">Senior management</td>
<td align="left">Master of Commerce</td>
<td align="left">Financial Management Sciences</td>
</tr>
<tr>
<td align="left">Participant 8</td>
<td align="left">Male</td>
<td align="left">Engineering firm</td>
<td align="left">15 years</td>
<td align="left">Senior management</td>
<td align="left">Master of Commerce</td>
<td align="left">Development Economics</td>
</tr>
<tr>
<td align="left">Participant 9</td>
<td align="left">Male</td>
<td align="left">Engineering firm</td>
<td align="left">10 years</td>
<td align="left">Senior management</td>
<td align="left">Bachelor of Science</td>
<td align="left">Quantity Surveying</td>
</tr>
<tr>
<td align="left">Participant 10</td>
<td align="left">Male</td>
<td align="left">Engineering firm</td>
<td align="left">38 years</td>
<td align="left">Senior management</td>
<td align="left">Bachelor of Science</td>
<td align="left">Electrical Engineering</td>
</tr>
<tr>
<td align="left">Participant 11</td>
<td align="left">Female</td>
<td align="left">Airline</td>
<td align="left">4 years</td>
<td align="left">Senior management</td>
<td align="left">Master of Business Administration</td>
<td align="left">Management</td>
</tr>
<tr>
<td align="left">Participant 12</td>
<td align="left">Male</td>
<td align="left">Engineering firm</td>
<td align="left">25 years</td>
<td align="left">Senior management</td>
<td align="left">Bachelor of Education</td>
<td align="left">Mathematics</td>
</tr>
<tr>
<td align="left">Participant 13</td>
<td align="left">Male</td>
<td align="left">State-owned airline</td>
<td align="left">18 years</td>
<td align="left">Senior management</td>
<td align="left">Bachelor of Commerce (Honours)</td>
<td align="left">Transport Economics</td>
</tr>
<tr>
<td align="left">Participant 14</td>
<td align="left">Male</td>
<td align="left">Airline</td>
<td align="left">7 years</td>
<td align="left">Senior management</td>
<td align="left">Bachelor of Commerce (Honours)</td>
<td align="left">Management Sciences</td>
</tr>
</tbody>
</table>
</table-wrap>
</sec>
<sec id="s20008">
<title>Reasons for the low uptake of transport public&#x2013;private partnerships in South Africa</title>
<p>The participants were requested to provide reasons why they believed there was a low uptake of PPPs in South Africa. The findings reveal the main view amongst the participants is the politicisation of infrastructure through party politics, political risk and the dominance of the state in the delivery of strategic infrastructure and assets, as confirmed by Participant 1. He felt that the uptake of transport PPPs was impeded by the pursuit of party political agendas to the detriment of projects that are in the public interest. He mentioned, as an example, the irrationality of the decision of politicians to forego the proposed De Beers Pass toll road concession, which would have provided a viable alternative route to the country&#x2019;s busiest port in Durban. Participant 6 was of the view that the political rhetoric on &#x2018;radical economic transformation and white monopoly&#x2019; had also harmed business confidence and trust, discouraging investment in PPPs. This finding was endorsed by Participant 5, who indicated the &#x2018;private sector wants to put their resources where they are going to be sure they are going to receive their return&#x2019;. Participant 11 thought &#x2018;the fear of the unknown from the public sector&#x2019; and the private sector&#x2019;s &#x2018;perception when it comes to the public sector&#x2019; have created this trust deficit between the two. Furthermore, Participant 13 affirmed the lack of trust between the two sectors and its impact on business confidence, as demonstrated by the &#x2018;very low business confidence throughout the period under review&#x2019;. He also stated that &#x2018;the private sector would not want to partner with somebody that they did not trust&#x2019;. Participant 10 indicated the lack of a <italic>PPP Act</italic> that could address the complexities and ambiguities associated with a broad regulatory framework that spans multiple policy instruments, which had undermined business confidence, resulting in a lack of uptake. These findings pinpoint a major cause of the low uptake amidst the possible reasons outlined in the literature. As a result, greater focus and effort can be directed to resolving this issue, leading to greater uptake.</p>
<p><xref ref-type="fig" rid="F0003">Figure 3</xref> displays a network diagram of the reasons for the low uptake of transport PPPs. Some of the responses showed that a few of the participants suggested the low uptake to be the result of ignorance of policymakers on the role of transport in the economy. This ignorance is linked to low initiative and uptake across all sectors, which results in small, uncomplicated projects being prioritised for implementation.</p>
<fig id="F0003">
<label>FIGURE 3</label>
<caption><p>Network diagram of the reasons for the low uptake of transport public&#x2013;private partnerships.</p></caption>
<graphic xmlns:xlink="http://www.w3.org/1999/xlink" xlink:href="JTSCM-16-733-g003.tif"/>
</fig>
</sec>
<sec id="s20009">
<title>Requirement for a specific law for public&#x2013;private partnership</title>
<p>The participants were further requested to provide opinions on whether they felt a specific law for PPP was required. The results show that participants felt the introduction of a <italic>PPP Act</italic> can contribute positively to addressing over-regulation, thereby attracting investment as confirmed by Participant 10. He felt a specific law would &#x2018;ring-fence the process&#x2019;, decoupling it from an amorphous application process. Participant 6 thought that this would lead to the easing of the regulation of PPPs, as the current regulatory framework was &#x2018;a bit too stringent&#x2019;. Participant 4 felt it would result in a faster approval process for PPPs by providing &#x2018;guidance on how to actually undertake that particular process, without relying just on policymakers&#x2019;. Participant 14 also believed that a specific law would provide an opportunity to focus regulations on activities that improve implementation by &#x2018;supporting private sector participation&#x2019;. Participant 3 was of the view that the introduction of a PPP Act would also contribute to promoting the inclusivity of marginalised communities by improving transparency in areas relating to the tariff structure. He felt the lack of regulation on how information was communicated made it possible for society to be misled. For example, he felt communication on aspects such as the determination of tariff structure for some of these projects &#x2018;is not entirely true&#x2019;, which could impede access to &#x2018;infrastructure that is open for all citizens and not only for those who can afford&#x2019;. Participant 2 also thought this law would &#x2018;provide the certainty that is required by the private partners before they can commit&#x2019;. He felt certainty would be brought about by knowing upfront the implications of the policy. Participant 8 thought a <italic>PPP Act</italic> would improve the collection of revenue as users would know that it was illegal not to pay. He stated &#x2018;people will not be in a position to not pay&#x2019;.</p>
<p>Another view that emerged was that a <italic>PPP Act</italic> was not required, and the existing regulatory framework needed to be kept or amended, as it was not inhibitive and could rather be improved to enable a more seamless private sector participation. This finding was confirmed by Participant 1, who stated, &#x2018;I don&#x2019;t find the regulations inhibiting at all, as long as you do the work that we have to do&#x2019;. He felt the regulations were not necessarily a problem, but the &#x2018;extremely low skills in South Africa [<italic>are</italic>], as far as PPPs are concerned&#x2019;. Participant 9 also thought a PPP Act was not necessary; he stated that &#x2018;just enabling policies that provide better incentives and access to the private sector&#x2019; would be sufficient.</p>
<p>What was not expected was the view of Participant 11, who felt that instead of a single law for all PPPs, the state should introduce sector-specific laws, as he commented that there was a requirement for &#x2018;legislation per sector&#x2019;. He stated that legislation needed to indicate &#x2018;how a sector should deal with it&#x2019; to address its specific circumstances. This finding augurs well with the tourism sector&#x2019;s practice, which has its own PPP toolkit as &#x2018;the PPP manual and Standardised PPP Provisions cannot, however, be summarily applied to tourism PPP projects&#x2019; (National Treasury <xref ref-type="bibr" rid="CIT0047">2015</xref>:1). Differentiated regulations for other sectors would assist the public and private sectors to enter into sector-specific PPPs by taking into consideration the special conditions in that sector (National Treasury <xref ref-type="bibr" rid="CIT0047">2015</xref>). For example, in the tourism sector there are special conditions such as:</p>
<disp-quote>
<p>[&#x2026; <italic>C</italic>] ircumstances involving communal land, or private land, which is under state conservation management, over which conservation institutions have acquired explicit commercial rights which they seek to exercise via a PPP. (National Treasury <xref ref-type="bibr" rid="CIT0047">2015</xref>:4)</p>
</disp-quote>
<p>In light of the findings that a specific law that would facilitate the PPP process could add value by decoupling the amorphous application process, a conclusion could be drawn that the need is not necessarily for an act but rather for an act that facilitates the PPP process. This is evidenced by Wei, Wenjuan and Xu (<xref ref-type="bibr" rid="CIT0074">2015</xref>) and Arimoro (<xref ref-type="bibr" rid="CIT0005">2018</xref>), who indicated that specific regulatory frameworks have contributed to the success of PPPs in some countries. A comparison of the BRICS countries shows that some of them have a specific <italic>PPP Act</italic>, such as Brazil, whilst some (like India and China) do not. This finding is important as it also suggests that a specific PPP Act in itself is not important, but the ability of the legal framework to facilitate the PPP process in an effective manner is.</p>
<p><xref ref-type="fig" rid="F0004">Figure 4</xref> displays the network diagram of responses on the need for a specific law for PPPs and the value it would add. It demonstrates that participants felt the introduction of a PPP Act would add value by decoupling the amorphous application process; easing regulation; improving the turnaround time of the approval processes; enhancing implementation, inclusivity and policy certainty; and ensuring the payment of services provided.</p>
<fig id="F0004">
<label>FIGURE 4</label>
<caption><p>Network diagram of responses on the need for a specific law for public&#x2013;private partnerships.</p></caption>
<graphic xmlns:xlink="http://www.w3.org/1999/xlink" xlink:href="JTSCM-16-733-g004.tif"/>
</fig>
</sec>
<sec id="s20010">
<title>Public consultation and participation</title>
<p>This study also reveals that there is a dominant view amongst participants on a lack of extensive public consultation and participation. These findings are confirmed by Participant 7, who stated &#x2018;the public did not participate in the consultation at the time when they were needed to participate&#x2019;. He asserted that the public only develops an interest closer to the implementation of the projects, when they become aware of how they are going to be affected. Participant 1 also indicated that although the <italic>South African National Roads Agency limited (SANRAL) Act</italic> and environmental impact assessment requirements make public participation compulsory in the road sector, they &#x2018;can&#x2019;t force people to come to the meetings&#x2019;. However, he indicated that this did not mean that consultation did not happen, as demonstrated by the findings of the Constitutional Court, which expressed that &#x2018;we had done what we needed to do&#x2019;. Participant 3 felt &#x2018;only the privileged and elite&#x2019; participated because they have access to information and technology. He felt disadvantaged members of society are disenfranchised by the lack of information. As a result, there was a lack of &#x2018;societal wide participation&#x2019;.</p>
<p>Participant 14 thought that the &#x2018;public consultation process isn&#x2019;t very advanced compared with other countries&#x2019;. This subjects the consultative process to several influences that can distort the outcome of the discussions. This finding was confirmed by Participant 1, who felt &#x2018;local municipalities don&#x2019;t have capacity to be able to engage with you&#x2019; where toll roads have to go. As a result, there were no meaningful exchanges or engagements, even though it is mandatory to consult. He also felt the lack of capacity to engage meaningfully was also a problem at the provincial level. Participant 13 was of the view that &#x2018;the National Treasury is not doing enough in socialising the idea of PPPs&#x2019;. He felt the mandate on PPPs &#x2018;had to move from Treasury&#x2019; to another ministry such as the Department of Public Enterprises, which &#x2018;would be a fitting ministry to look after PPPs&#x2019;. Participant 10 indicated that there is &#x2018;complete mistrust&#x2019; of the consultation process. He felt that even before the process is undertaken, there was a sense of who would be the successful bidder. This finding was endorsed by Participant 9, who thought &#x2018;public consultation tends to be politically driven&#x2019;. As a result, the effectiveness of participation was limited.</p>
<p>Contrary to most of the participants&#x2019; views, Participant 6 thought there was extensive public consultation and participation. He attributed his thoughts to the success of the Gautrain Rapid Rail Project, which he felt &#x2018;was done well&#x2019;. Participant 5 also felt &#x2018;government is trying really a lot in terms of public consultations&#x2019;, based on the &#x2018;imbizos that the different departments will undertake with their constituencies&#x2019;. An imbizo refers to an official gathering between the state and the public, where members of the executive interact closely with the public (Government of South Africa <xref ref-type="bibr" rid="CIT0022">2020</xref>).</p>
<p>Based on the findings, it could be concluded that there is a lack of extensive public consultation and participation. These findings are evidenced by Aigbavboa et al. (<xref ref-type="bibr" rid="CIT0002">2014</xref>), who suggested that South Africa does not seem to be conducting extensive public participation and consultation to promote the public interest.</p>
<p><xref ref-type="fig" rid="F0005">Figure 5</xref> depicts the network diagram of the responses of the public consultation and their participation. It shows that participants felt that the lack of consultation and participation emanates from low public interest, the inability to force people to participate and an interest only by the privileged and elite. It also showed that the participants felt the consultation processes are unsophisticated, as there was a lack of a guiding methodology to the process, the local government had limited capacity to engage and the National Treasury was not doing enough to generate awareness. Furthermore, there was complete distrust of this process, and it was seen as being politically driven. It also showed that two participants did not share the view that there was not extensive public consultation, as demonstrated by the success of the Gautrain project and the imbizos that are held by the government.</p>
<fig id="F0005">
<label>FIGURE 5</label>
<caption><p>Network diagram of responses to public consultation.</p></caption>
<graphic xmlns:xlink="http://www.w3.org/1999/xlink" xlink:href="JTSCM-16-733-g005.tif"/>
</fig>
<p>Other areas that were highlighted by the participants that could improve the uptake of transport PPPs in South Africa include enhancing the skills of public officials. To this end, participants felt that training can be promoted as a measure to improve the capacity of officials to deliver on projects. They were of the view that capacity can be developed through approaches such as an international exchange programme with the BRICS countries and a skills transfer programme by the private sector. Participants also thought the proactive disclosure of the project and contract information was required to promote good governance. This finding is confirmed by Wei et al. (<xref ref-type="bibr" rid="CIT0074">2015</xref>), who indicated that proactive disclosure is important for good governance. Furthermore, the establishment of PPP units at subnational levels is required to improve capacity throughout the state (i.e. both provincial and municipal). This finding is evidenced by Ittmann (<xref ref-type="bibr" rid="CIT0031">2017</xref>), who suggested that the establishment of PPP units at a subnational level could result in the proliferation of PPPs in the transport sector.</p>
<p>Participants also felt that a regional credit rating agency needs to be established, as it would be influential over the decision of investors to finance PPPs in the country and the rest of the region. This finding is confirmed by the Africa Report (<xref ref-type="bibr" rid="CIT0067">2014</xref>), which stated that the establishment of a regional rating agency would contribute towards alleviating the fears of investors by providing in-depth information on entities operating across the region. The number of competitors in the PPP market is also largely perceived to be inadequate. It is not apparent from the literature how robust the level of competition is in the South African PPP market (Aigbavboa et al. <xref ref-type="bibr" rid="CIT0002">2014</xref>; Makofane <xref ref-type="bibr" rid="CIT0040">2013</xref>; National Treasury <xref ref-type="bibr" rid="CIT0049">2017</xref>). This is evidenced by the PPP database of the GTAC, which only highlights the successful bidder (GTAC <xref ref-type="bibr" rid="CIT0024">2019</xref>). The participants felt that the lack of competition and participation could be addressed through advocacy of the benefits of PPPs to all industry role players, and this would encourage competitive bidding.</p>
</sec>
</sec>
<sec id="s0011">
<title>Conclusion</title>
<p>The findings from the secondary data show that there is a need to strengthen political commitment and support for PPPs by centralising and coordinating planning efforts for PPPs across the different tiers of government in view of improving state capacity and identifying projects with the greatest probability of success. The primary data indicate a need for easing the regulatory burden associated with PPPs to make them simpler to implement and attractive for private sector involvement by promoting inclusivity, policy certainty and the payment of services provided.</p>
<p>Notwithstanding the limitations of the study, such as the use of a small sample based on limited PPP application in South Africa&#x2019;s transport sector, the research provides a description of the problems with transport PPPs in the country. It can also serve as a basis for future research. Policymakers can utilise these results to strengthen political support and commitment to transport PPPs by translating rhetoric into actionable plans. Transport PPPs should also appear more prominently in the budgets and plans of the different tiers of government. Furthermore, policies for private sector access and the knowledge of officials on public processes required for establishing PPP projects need to be improved. To address the regulatory burden, the introduction of a PPP Act or an act that facilitates the process could also be beneficial by addressing the inadequacies of the current regulatory framework (which comprises the PFMA and other legislation), making compliance simpler and promoting innovation and inclusivity. Public participation can be strengthened through social facilitation efforts. To address the trust deficit that exists between the public and private sectors, greater levels of trust need to be fostered to allay suspicions they have of each other&#x2019;s motives. This trust would be achieved by promoting greater transparency of processes and decision-making to assure investors that decisions are honest. Stanley and David (<xref ref-type="bibr" rid="CIT0063">2008</xref>) also show that lessons from contracting route bus services in Melbourne indicate that trust can be fostered by extending key performance indicators beyond the private party to include the public sector authority and spread performance pressure to both parties in order to highlight the interdependence of a true partnership. The foundation for trust should also be developed at a precontractual phase to encourage transparency and accountability (Stanley &#x0026; David <xref ref-type="bibr" rid="CIT0063">2008</xref>).</p>
<p>Proactive disclosure of project information can help in this regard. The establishment of a regional credit rating agency could also attract greater investment if implemented in an unbiased manner. Competition can also be encouraged by increasing the number of available projects. This could be achieved by:</p>
<disp-quote>
<p>[&#x2026; <italic>P</italic>]utting in place a strong pipeline of smaller PPP projects under &#x2018;framework&#x2019; type agreements that streamline processes and reduce bid costs in sectors with a high number of PPP projects. (KPMG <xref ref-type="bibr" rid="CIT0035">2010</xref>:45)</p>
</disp-quote>
<p>Preferential procurement could be considered to introduce new local players by subcontracting a percentage of contracts to smaller companies whilst facilitating appropriate skills transfer. Future research on the mitigation of political risk in large infrastructure projects could also prove useful in improving private sector participation.</p>
</sec>
</body>
<back>
<ack>
<title>Acknowledgements</title>
<sec id="s20012" sec-type="COI-statement">
<title>Competing interests</title>
<p>The authors declare that they have no financial or personal relationships that may have inappropriately influenced them in writing this article.</p>
</sec>
<sec id="s20013">
<title>Authors&#x2019; contributions</title>
<p>O.K.S. was responsible for conceptualising and writing the research report. T.M. was the research supervisor and R.L. was the co-supervisor.</p>
</sec>
<sec id="s20014">
<title>Ethical considerations</title>
<p>Ethical clearance was granted for the study by the Departmental Ethics Committee of the Department of Transport and Supply Chain Management, University of Johannesburg (ref. no. 2019TSCM-0004MA).</p>
</sec>
<sec id="s20015">
<title>Funding information</title>
<p>This research received no specific grant from any funding agency in the public, commercial or not-for-profit sectors.</p>
</sec>
<sec id="s20016">
<title>Data availability</title>
<p>Secondary data were obtained from the following websites: <ext-link ext-link-type="uri" xlink:href="https://ppi.worldbank.org/en/ppi">https://ppi.worldbank.org/en/ppi</ext-link> and <ext-link ext-link-type="uri" xlink:href="https://www.gtac.gov.za/tenders/ppp-tenders/">https://www.gtac.gov.za/tenders/ppp-tenders/</ext-link></p>
</sec>
<sec id="s20017">
<title>Disclaimer</title>
<p>The views and opinions expressed are those of the authors and do not necessarily reflect the official policy or position of any affiliated agency of the authors.</p>
</sec>
</ack>
<ref-list id="references">
<title>References</title>
<ref id="CIT0001"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Agarchand</surname>, <given-names>N</given-names></string-name>. &#x0026; <string-name><surname>Laishram</surname>, <given-names>B</given-names></string-name></person-group>., <year>2017</year>, &#x2018;<article-title>Sustainable infrastructure development challenges through PPP procurement process</article-title>&#x2019;, <source><italic>International Journal of Managing Projects in Business</italic></source> <volume>10</volume>(<issue>3</issue>), <fpage>642</fpage>&#x2013;<lpage>662</lpage>. <comment><ext-link ext-link-type="uri" xlink:href="https://doi.org/10.1108/IJMPB-10-2016-0078">https://doi.org/10.1108/IJMPB-10-2016-0078</ext-link></comment></mixed-citation></ref>
<ref id="CIT0002"><mixed-citation publication-type="conference"><person-group person-group-type="author"><string-name><surname>Aigbavboa</surname>, <given-names>C.O</given-names></string-name>., <string-name><surname>Liphadzi</surname>, <given-names>M</given-names></string-name>. &#x0026; <string-name><surname>Thwala</surname>, <given-names>W.D</given-names></string-name></person-group>., <year>2014</year>, &#x2018;<article-title>An exploration of public private partnership in infrastructure development in South Africa</article-title>&#x2019;, in <person-group person-group-type="editor"><string-name><given-names>S</given-names>. <surname>Laryea</surname></string-name> &#x0026; <string-name><given-names>E</given-names>. <surname>Ibem</surname></string-name> (eds.)</person-group>, <conf-name>Proceedings 8th construction industry development board (CIDB) postgraduate conference</conf-name>, <conf-date>10&#x2013;11 February 2014</conf-date>, pp. <fpage>101</fpage>&#x2013;<lpage>109</lpage>, <publisher-name>University of the Witwatersrand</publisher-name>, <publisher-loc>Johannesburg</publisher-loc>, <comment>viewed 15 April 2018, from <ext-link ext-link-type="uri" xlink:href="http://hdl.handle.net/10210/12044">http://hdl.handle.net/10210/12044</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0003"><mixed-citation publication-type="journal"><person-group person-group-type="author"><collab>APM Group</collab></person-group>, <year>2020</year>, <source><italic>Term definition</italic></source>, <comment>viewed 10 July 2020, from <ext-link ext-link-type="uri" xlink:href="https://ppp-certification.com/ppp-certification-guide/41-term-definition">https://ppp-certification.com/ppp-certification-guide/41-term-definition</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0004"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Arata</surname>, <given-names>M</given-names></string-name>., <string-name><surname>Petrangeli</surname>, <given-names>M</given-names></string-name>. &#x0026; <string-name><surname>Longo</surname>, <given-names>F</given-names></string-name></person-group>., <year>2016</year>, &#x2018;<article-title>Innovative approaches to implement road infrastructure concession through Public-Private Partnership (PPP) initiatives: A case study</article-title>&#x2019;, <source><italic>Transportation Research Procedia</italic></source> <volume>14</volume>, <fpage>343</fpage>&#x2013;<lpage>352</lpage>. <comment><ext-link ext-link-type="uri" xlink:href="https://doi.org/10.1016/j.trpro.2016.05.086">https://doi.org/10.1016/j.trpro.2016.05.086</ext-link></comment></mixed-citation></ref>
<ref id="CIT0005"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Arimoro</surname>, <given-names>A</given-names></string-name></person-group>., <year>2018</year>, &#x2018;<article-title>An appraisal of the framework for public private partnership in South Africa</article-title>&#x2019;, <source><italic>European Procurement &#x0026; Public Private Partnership Law Review</italic></source> <volume>13</volume>(<issue>3</issue>), <fpage>214</fpage>&#x2013;<lpage>228</lpage>. <comment><ext-link ext-link-type="uri" xlink:href="https://doi.org/10.21552/epppl/2018/3/8">https://doi.org/10.21552/epppl/2018/3/8</ext-link></comment></mixed-citation></ref>
<ref id="CIT0006"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Barr</surname>, <given-names>M</given-names></string-name></person-group>., <year>2020</year>, <source><italic>The long and short of it: Lifespans of paved roadways</italic></source>, <comment>viewed 26 July 2020, from <ext-link ext-link-type="uri" xlink:href="https://www.ayresassociates.com/the-long-and-short-of-it-lifespans-of-paved-roadways/">https://www.ayresassociates.com/the-long-and-short-of-it-lifespans-of-paved-roadways/</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0007"><mixed-citation publication-type="book"><person-group person-group-type="author"><string-name><surname>Beck</surname>, <given-names>T</given-names></string-name>., <string-name><surname>Mainmbo</surname>, <given-names>S</given-names></string-name>., <string-name><surname>Faye</surname>, <given-names>I</given-names></string-name>. &#x0026; <string-name><surname>Triki</surname>, <given-names>T</given-names></string-name></person-group>., <year>2011</year>, <source><italic>Financing Africa: Through the crisis and beyond</italic></source>, <publisher-name>World Bank</publisher-name>, <publisher-loc>Washington, DC</publisher-loc>.</mixed-citation></ref>
<ref id="CIT0008"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Beerbohm</surname>, <given-names>M</given-names></string-name>. &#x0026; <string-name><surname>Fitzgerald</surname>, <given-names>E</given-names></string-name></person-group>., <year>2019</year>, <source>Feasibility study and business plan: Learn how to present a completed feasibility study</source>, <comment>Independently published</comment>.</mixed-citation></ref>
<ref id="CIT0009"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Bloomfield</surname>, <given-names>P</given-names></string-name>. &#x0026; <string-name><surname>Ahern</surname>, <given-names>D</given-names></string-name></person-group>., <year>2011</year>, &#x2018;<article-title>Long-term infrastructure projects: Contracting risks and risk-reduction strategies</article-title>&#x2019;, <source><italic>State &#x0026; Local Government Review</italic></source> <volume>43</volume>(<issue>1</issue>), <fpage>49</fpage>&#x2013;<lpage>59</lpage>. <comment><ext-link ext-link-type="uri" xlink:href="https://doi.org/10.1177/0160323X11400435">https://doi.org/10.1177/0160323X11400435</ext-link></comment></mixed-citation></ref>
<ref id="CIT0010"><mixed-citation publication-type="journal"><person-group person-group-type="author"><collab>Cambridge University Press</collab></person-group>, <year>2017</year>, <source><italic>Cambridge advanced learner&#x2019;s dictionary &#x0026; thesaurus, definition of best practice by the online dictionary</italic></source>, <comment>viewed 07 May 2018, from <ext-link ext-link-type="uri" xlink:href="http://dictionary.cambridge.org/dictionary/english/best-practice">http://dictionary.cambridge.org/dictionary/english/best-practice</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0011"><mixed-citation publication-type="journal"><person-group person-group-type="author"><collab>Chartered Institute of Procurement and Supply</collab></person-group>, <year>n.d.</year>, <source><italic>Contract management cycle</italic></source>, <comment>viewed 18 February 2019, from <ext-link ext-link-type="uri" xlink:href="https://www.cips.org/en-ZA/knowledge/contract-management-cycle/">https://www.cips.org/en-ZA/knowledge/contract-management-cycle/</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0012"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Churakov</surname>, <given-names>R</given-names></string-name></person-group>., <year>2014</year>, &#x2018;<article-title>Trends: How Russian PPP are changing</article-title>&#x2019;, <source>International Financial Law Review</source>, p. <fpage>52</fpage>, <comment>viewed 04 August 2018, from <ext-link ext-link-type="uri" xlink:href="https://search.ebscohost.com/login.aspx?direct=true&#x0026;AuthType=sso&#x0026;db=bsu&#x0026;AN=96676978&#x0026;site=ehost-live&#x0026;scope=site">https://search.ebscohost.com/login.aspx?direct=true&#x0026;AuthType=sso&#x0026;db=bsu&#x0026;AN=96676978&#x0026;site=ehost-live&#x0026;scope=site</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0013"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Cruz</surname>, <given-names>C</given-names></string-name>., <string-name><surname>Marques</surname>, <given-names>R</given-names></string-name>. &#x0026; <string-name><surname>Franco</surname>, <given-names>D</given-names></string-name></person-group>., <year>2015</year>, &#x2018;<article-title>Road-network development in quickly growing economies: Brazilian case study MG-050</article-title>&#x2019;, <source><italic>Journal of Infrastructure Systems</italic></source> <volume>21</volume>(<issue>4</issue>), <fpage>1</fpage>&#x2013;<lpage>7</lpage>. <comment><ext-link ext-link-type="uri" xlink:href="https://doi.org/10.1061/(ASCE)IS.1943-555X.0000254">https://doi.org/10.1061/(ASCE)IS.1943-555X.0000254</ext-link></comment></mixed-citation></ref>
<ref id="CIT0014"><mixed-citation publication-type="conference"><person-group person-group-type="author"><string-name><surname>Dachs</surname>, <given-names>W</given-names></string-name></person-group>., <year>2011</year>, &#x2018;<article-title>Gautrain: Public money in a private deal</article-title>&#x2019;, Presentation at the <conf-name>IFC PPP conference</conf-name> held at <conf-loc>Lagos in Nigeria</conf-loc> on <conf-date>November 2011</conf-date>, <publisher-loc>Midrand</publisher-loc>: <publisher-name>Gautrain management Agency</publisher-name>, <comment>viewed 23 May 2019, from <ext-link ext-link-type="uri" xlink:href="https://www.ifc.org/wps/wcm/connect/48abc6b0-f584-41fe-9d23-4e2c7bf830d5/3.1_Public+Money&#x0025;2C+Private+Deals+-+Public+Sector+Financing+Trends+-+Gautrain+-+William+Dachs.pdf?MOD=AJPERES&#x0026;CVID=jgq3.Bl">https://www.ifc.org/wps/wcm/connect/48abc6b0-f584-41fe-9d23-4e2c7bf830d5/3.1_Public+Money&#x0025;2C+Private+Deals+-+Public+Sector+Financing+Trends+-+Gautrain+-+William+Dachs.pdf?MOD=AJPERES&#x0026;CVID=jgq3.Bl</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0015"><mixed-citation publication-type="book"><person-group person-group-type="author"><collab>Deloitte</collab></person-group>, <year>2018</year>, <source><italic>Project bonds: An alternative source of financing infrastructure projects</italic></source>, <publisher-name>Deloitte</publisher-name>, <publisher-loc>Johannesburg</publisher-loc>, <comment>viewed 25 September 2018, from <ext-link ext-link-type="uri" xlink:href="https://www2.deloitte.com/za/en/pages/finance/articles/project-bonds-an-alternative-to-financing-infrastructure-projects.html">https://www2.deloitte.com/za/en/pages/finance/articles/project-bonds-an-alternative-to-financing-infrastructure-projects.html</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0016"><mixed-citation publication-type="book"><person-group person-group-type="author"><string-name><surname>Delmon</surname>, <given-names>J</given-names></string-name></person-group>., <year>2017</year>, <source><italic>Public-private partnerships in infrastructure: An essential guide for policy makers</italic></source>, <edition>2nd</edition> edn., <publisher-name>Cambridge University Press</publisher-name>, <publisher-loc>New York, NY</publisher-loc>.</mixed-citation></ref>
<ref id="CIT0017"><mixed-citation publication-type="journal"><person-group person-group-type="author"><collab>Department of Economic Affairs</collab></person-group>, <year>2010</year>, <source><italic>Developing toolkits for improving public private partnership decision making processes</italic></source>, <comment>viewed 09 June 2022, from <ext-link ext-link-type="uri" xlink:href="https://www.pppinindia.gov.in/toolkit/pdf/ppp_toolkit_user_guide.pdf">https://www.pppinindia.gov.in/toolkit/pdf/ppp_toolkit_user_guide.pdf</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0018"><mixed-citation publication-type="journal"><person-group person-group-type="author"><collab>Food and Agriculture Organisation of the United Nations</collab></person-group>, <year>2019</year>, <source><italic>Chapter 5: Personal interviews</italic></source>, <comment>viewed 20 August 2019, from <ext-link ext-link-type="uri" xlink:href="http://www.fao.org/3/w3241e/w3241e06.html">http://www.fao.org/3/w3241e/w3241e06.html</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0019"><mixed-citation publication-type="journal"><person-group person-group-type="author"><collab>Gilbert and Tobin</collab></person-group>, <year>2020</year>, <source><italic>Are public private partnerships (PPP) dead?</italic></source>, <comment>viewed 21 June 2022, from <ext-link ext-link-type="uri" xlink:href="https://www.gtlaw.com.au/insights/are-public-private-partnerships-ppps-dead">https://www.gtlaw.com.au/insights/are-public-private-partnerships-ppps-dead</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0020"><mixed-citation publication-type="journal"><person-group person-group-type="author"><collab>Global Infrastructure Hub</collab></person-group>, <year>2016</year>, <source><italic>Allocating risks in public-private partnership contracts</italic></source>, <comment>viewed 05 July 2020, from <ext-link ext-link-type="uri" xlink:href="https://library.pppknowledgelab.org/documents/3523/download">https://library.pppknowledgelab.org/documents/3523/download</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0021"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Gopalkrishna</surname>, <given-names>N</given-names></string-name>. &#x0026; <string-name><surname>Karnam</surname>, <given-names>G</given-names></string-name></person-group>., <year>2015</year>, &#x2018;<article-title>Performance analysis of national highways public private partnerships in India</article-title>&#x2019;, <source><italic>Public Works Management &#x0026; Policy</italic></source> <volume>20</volume>(<issue>3</issue>), <fpage>264</fpage>&#x2013;<lpage>285</lpage>. <comment><ext-link ext-link-type="uri" xlink:href="https://doi.org/10.1177/1087724X14558270">https://doi.org/10.1177/1087724X14558270</ext-link></comment></mixed-citation></ref>
<ref id="CIT0022"><mixed-citation publication-type="book"><person-group person-group-type="author"><collab>Government of South Africa</collab></person-group>, <year>2020</year>, <source><italic>National Imbizo focus week</italic></source>, <publisher-name>Government of South Africa</publisher-name>, <publisher-loc>Pretoria</publisher-loc>, <comment>viewed 29 August 2020, from <ext-link ext-link-type="uri" xlink:href="https://www.gov.za/national-imbizo-focus-week">https://www.gov.za/national-imbizo-focus-week</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0023"><mixed-citation publication-type="journal"><person-group person-group-type="author"><collab>Government Technical Advisory Centre (GTAC)</collab></person-group>, <year>2016</year>, <source><italic>Projects</italic></source>, <comment>Database of closed and active PPP projects, viewed 15 October 2018, from <ext-link ext-link-type="uri" xlink:href="https://www.gtac.gov.za/Pages/Project.aspx?Paged=TRUE&#x0026;p_Government_x0020_System=Public&#x0025;20Entities&#x0026;p_ID=31&#x0026;PageFirstRow=61&#x0026;&#x0026;View={D5EEF9F3-113A-4787-9CE0-4920C07BE6B7}">https://www.gtac.gov.za/Pages/Project.aspx?Paged=TRUE&#x0026;p_Government_x0020_System=Public&#x0025;20Entities&#x0026;p_ID=31&#x0026;PageFirstRow=61&#x0026;&#x0026;View={D5EEF9F3-113A-4787-9CE0-4920C07BE6B7}</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0024"><mixed-citation publication-type="journal"><person-group person-group-type="author"><collab>Government Technical Advisory Centre (GTAC)</collab></person-group>, <year>2019</year>, <source><italic>Projects in preparation, registered in terms of Treasury Regulation 16 and municipal projects registered under the MFMA and MSA as at May 2019</italic></source>, <comment>viewed 09 October 2019, from <ext-link ext-link-type="uri" xlink:href="https://www.gtac.gov.za/Publications/Project&#x0025;20List&#x0025;20for&#x0025;20the&#x0025;20PPP&#x0025;20Quarterly&#x0025;20May&#x0025;202019.pdf">https://www.gtac.gov.za/Publications/Project&#x0025;20List&#x0025;20for&#x0025;20the&#x0025;20PPP&#x0025;20Quarterly&#x0025;20May&#x0025;202019.pdf</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0025"><mixed-citation publication-type="book"><person-group person-group-type="author"><collab>Gray</collab></person-group>, <year>n.d.</year>, <source><italic>Greenfield vs. brownfield: What&#x2019;s better for your manufacturing facility, Gray</italic></source>, <publisher-loc>Lexington</publisher-loc>, <comment>viewed 22 July 2022, from <ext-link ext-link-type="uri" xlink:href="http://gray.com/insights/greenfield-vs-brownfield-whats-better-for-your-manufacturing-facility/">http://gray.com/insights/greenfield-vs-brownfield-whats-better-for-your-manufacturing-facility/</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0026"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Guo</surname>, <given-names>G</given-names></string-name>., <string-name><surname>Martek</surname>, <given-names>I</given-names></string-name>. &#x0026; <string-name><surname>Chuan</surname>, <given-names>C</given-names></string-name></person-group>., <year>2019</year>, &#x2018;<article-title>Policy evolution in the Chinese PPP market: The shifting strategies of governmental support measures</article-title>&#x2019;, <source><italic>Sustainability</italic></source> <volume>11</volume>(<issue>18</issue>), <fpage>1</fpage>&#x2013;<lpage>24</lpage>. <comment><ext-link ext-link-type="uri" xlink:href="https://doi.org/10.3390/su11184872">https://doi.org/10.3390/su11184872</ext-link></comment></mixed-citation></ref>
<ref id="CIT0027"><mixed-citation publication-type="book"><person-group person-group-type="author"><collab>International Bank for Reconstruction and Development/The World Bank (IBRD/WB)</collab></person-group>, <year>2014</year>, <source><italic>Public-private partnerships: Reference guide, Version 2.0</italic></source>, <publisher-name>World Bank Publications</publisher-name>, <publisher-loc>Washington, DC</publisher-loc>.</mixed-citation></ref>
<ref id="CIT0028"><mixed-citation publication-type="book"><person-group person-group-type="author"><collab>International Bank for Reconstruction and Development/The World Bank (IBRD/WB)</collab></person-group>, <year>2017</year>, <source><italic>Public-private partnerships: Reference guide, Version 3.0</italic></source>, <publisher-name>World Bank Publications</publisher-name>, <publisher-loc>Washington, DC</publisher-loc>.</mixed-citation></ref>
<ref id="CIT0029"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Iossa</surname>, <given-names>E</given-names></string-name>. &#x0026; <string-name><surname>Martimort</surname>, <given-names>D</given-names></string-name></person-group>., <year>2012</year>, &#x2018;<article-title>Risk allocation and the costs and benefits of public-private partnerships</article-title>&#x2019;, <source><italic>The RAND Journal of Economics</italic></source> <volume>43</volume>(<issue>3</issue>), <fpage>442</fpage>&#x2013;<lpage>474</lpage>. <comment><ext-link ext-link-type="uri" xlink:href="https://doi.org/10.1111/j.1756-2171.2012.00181.x">https://doi.org/10.1111/j.1756-2171.2012.00181.x</ext-link></comment></mixed-citation></ref>
<ref id="CIT0030"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Istrate</surname>, <given-names>E</given-names></string-name>. &#x0026; <string-name><surname>Puentes</surname>, <given-names>R</given-names></string-name></person-group>., <year>2011</year>, <source><italic>Moving forward on public private partnerships: U.S. and international experience with PPP units</italic></source>, <comment>viewed 15 August 2018, from <ext-link ext-link-type="uri" xlink:href="http://ppp.worldbank.org/public-private-partnership/library/moving-forward-public-private-partnerships-us-and-international-experience-ppp-units">http://ppp.worldbank.org/public-private-partnership/library/moving-forward-public-private-partnerships-us-and-international-experience-ppp-units</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0031"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Ittmann</surname>, <given-names>H</given-names></string-name></person-group>., <year>2017</year>, &#x2018;<article-title>Private-public partnerships: A mechanism for freight transport infrastructure delivery?</article-title>&#x2019;, <source><italic>Journal of Transport and Supply Chain Management</italic></source> <volume>11</volume>, <fpage>13</fpage>. <comment><ext-link ext-link-type="uri" xlink:href="https://doi.org/10.4102/jtscm.v11i0.262">https://doi.org/10.4102/jtscm.v11i0.262</ext-link></comment></mixed-citation></ref>
<ref id="CIT0032"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Johnston</surname>, <given-names>J</given-names></string-name>. &#x0026; <string-name><surname>Kouzmin</surname>, <given-names>A</given-names></string-name></person-group>., <year>2010</year>, &#x2018;<article-title>Addressing governance, accountability and performance monitoring issues in partnerships: Can &#x201C;Infrastructure Australia&#x201D; provide a strategic response?</article-title>&#x2019;, <source><italic>Public Administration Quarterly</italic></source> <volume>34</volume>(<issue>4</issue>), <fpage>513</fpage>&#x2013;<lpage>551</lpage>, <comment>viewed 02 April 2018, from <ext-link ext-link-type="uri" xlink:href="http://www.jstor.org/stable/41288360">http://www.jstor.org/stable/41288360</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0033"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Jones</surname>, <given-names>L</given-names></string-name>. &#x0026; <string-name><surname>Bloomfield</surname>, <given-names>M</given-names></string-name></person-group>., <year>2020</year>, &#x2018;<article-title>PPP in China: Does the growth in Chinese PPP signal a liberalising economy?</article-title>&#x2019;, <source><italic>New Political Economy</italic></source> <volume>25</volume>(<issue>5</issue>), <fpage>829</fpage>&#x2013;<lpage>847</lpage>. <comment><ext-link ext-link-type="uri" xlink:href="https://doi.org/10.1080/13563467.2020.1721451">https://doi.org/10.1080/13563467.2020.1721451</ext-link></comment></mixed-citation></ref>
<ref id="CIT0034"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Koskela</surname>, <given-names>L</given-names></string-name>., <string-name><surname>Rooke</surname>, <given-names>J</given-names></string-name>. &#x0026; <string-name><surname>Siriwardena</surname>, <given-names>M</given-names></string-name></person-group>., <year>2016</year>, &#x2018;<article-title>Evaluation of the promotion of through-life management in public private partnerships for infrastructure</article-title>&#x2019;, <source><italic>Sustainability</italic></source> <volume>8</volume>(<issue>6</issue>), <fpage>552</fpage>. <comment><ext-link ext-link-type="uri" xlink:href="https://doi.org/10.3390/su8060552">https://doi.org/10.3390/su8060552</ext-link></comment></mixed-citation></ref>
<ref id="CIT0035"><mixed-citation publication-type="book"><person-group person-group-type="author"><collab>KPMG</collab></person-group>, <year>2010</year>, <source>PPP procurement: Review of barriers to competition and efficiency in the procurement of PPP projects</source>, <publisher-name>KPMG Corporate Finance</publisher-name>, <publisher-loc>Delaware</publisher-loc>.</mixed-citation></ref>
<ref id="CIT0036"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Leighland</surname>, <given-names>J</given-names></string-name></person-group>., <year>2018</year>, &#x2018;<article-title>Public-private partnerships in developing countries: The emerging evidence-based critique</article-title>&#x2019;, <source><italic>The World Bank Research Observer</italic></source> <volume>33</volume>(<issue>1</issue>), <fpage>103</fpage>&#x2013;<lpage>134</lpage>. <comment><ext-link ext-link-type="uri" xlink:href="https://doi.org/10.1093/wbro/lkx008">https://doi.org/10.1093/wbro/lkx008</ext-link></comment></mixed-citation></ref>
<ref id="CIT0037"><mixed-citation publication-type="book"><person-group person-group-type="author"><string-name><surname>Lodge</surname>, <given-names>M</given-names></string-name>., <string-name><surname>Van Stolk</surname>, <given-names>C</given-names></string-name>., <string-name><surname>Batistella-Machado</surname>, <given-names>J</given-names></string-name>., <string-name><surname>Schweppenstedde</surname>, <given-names>D</given-names></string-name>. &#x0026; <string-name><surname>Stepanek</surname>, <given-names>M</given-names></string-name></person-group>., <year>2017</year>, <source><italic>Regulation of logistics infrastructure in Brazil</italic></source>, <publisher-name>RAND Corporation</publisher-name>, <publisher-loc>Santa Monica, CA</publisher-loc>, <comment>viewed 09 June 2022, from <ext-link ext-link-type="uri" xlink:href="https://www.rand.org/content/dam/rand/pubs/research_reports/RR1900/RR1992/RAND_RR1992.pdf">https://www.rand.org/content/dam/rand/pubs/research_reports/RR1900/RR1992/RAND_RR1992.pdf</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0038"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Lukmanova</surname>, <given-names>I</given-names></string-name>. &#x0026; <string-name><surname>Mishlanova</surname>, <given-names>M</given-names></string-name></person-group>., <year>2015</year>, &#x2018;<article-title>Determinant analysis of public&#x2013;private partnerships in Russia</article-title>&#x2019;, <source><italic>International Journal of Economics and Financial Issues</italic></source> <volume>5</volume>(<issue>3</issue>), <fpage>208</fpage>&#x2013;<lpage>216</lpage>, <comment>viewed 12 May 2018, from <ext-link ext-link-type="uri" xlink:href="http://www.econjournals.com/index.php/ijefi/article/viewFile/1715/pdf">http://www.econjournals.com/index.php/ijefi/article/viewFile/1715/pdf</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0039"><mixed-citation publication-type="book"><person-group person-group-type="author"><string-name><surname>Macnee</surname>, <given-names>C</given-names></string-name>. &#x0026; <string-name><surname>McCabe</surname>, <given-names>S</given-names></string-name></person-group>., <year>2008</year>, <source><italic>Understanding nursing research: Reading and using research in evidence-based practice</italic></source>, <edition>2nd</edition> edn., <publisher-name>Lippincott Williams and Wilkins</publisher-name>, <publisher-loc>London</publisher-loc>.</mixed-citation></ref>
<ref id="CIT0040"><mixed-citation publication-type="book"><person-group person-group-type="author"><string-name><surname>Makofane</surname>, <given-names>T</given-names></string-name></person-group>., <year>2013</year>, <source><italic>Public private partnership in South Africa with reference to the realization of Black economic empowerment</italic></source>, <publisher-name>University of Pretoria</publisher-name>, <publisher-loc>Pretoria</publisher-loc>, <comment>viewed 20 November 2018, from <ext-link ext-link-type="uri" xlink:href="https://repository.up.ac.za/bitstream/handle/2263/24198/Complete.pdf?sequence=10&#x0026;isAllowed=y">https://repository.up.ac.za/bitstream/handle/2263/24198/Complete.pdf?sequence=10&#x0026;isAllowed=y</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0041"><mixed-citation publication-type="conference"><person-group person-group-type="author"><string-name><surname>Mandri-Perrott</surname>, <given-names>C</given-names></string-name></person-group>., <year>n.d.</year>, &#x2018;<article-title>Public-private partnerships (PPP) and infrastructure financing</article-title>&#x2019;, <conf-name>Presentation from the Singapore MFA Programme on PPP</conf-name> held from the <conf-date>16&#x2013;15 October 2015</conf-date>, <conf-loc>Nanyang Technological University (School of Civil and Environmental Engineering), Singapore</conf-loc>.</mixed-citation></ref>
<ref id="CIT0042"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Mansor</surname>, <given-names>N</given-names></string-name>. &#x0026; <string-name><surname>Rashid</surname>, <given-names>K</given-names></string-name></person-group>., <year>2016</year>, &#x2018;<article-title>Incomplete contract in Private Finance Initiative (PFI) contracts: Causes, implications and strategies</article-title>&#x2019;, <source><italic>Procedia &#x2013; Social and Behavioral Sciences</italic></source> <volume>222</volume>, <fpage>93</fpage>&#x2013;<lpage>102</lpage>. <comment><ext-link ext-link-type="uri" xlink:href="https://doi.org/10.1016/j.sbspro.2016.05.193">https://doi.org/10.1016/j.sbspro.2016.05.193</ext-link></comment></mixed-citation></ref>
<ref id="CIT0043"><mixed-citation publication-type="book"><person-group person-group-type="author"><string-name><surname>Marquaire</surname>, <given-names>J</given-names></string-name></person-group>., <year>2020</year>, &#x2018;<chapter-title>Infrastructure and public private partnerships</chapter-title>&#x2019;, <source><italic>Doing business in Russia</italic></source>, <publisher-name>CMS International</publisher-name>, <publisher-loc>Moscow</publisher-loc>, <comment>viewed 08 June 2022, from <ext-link ext-link-type="uri" xlink:href="https://cms-law.ru/en/rus/publication/doing-business-in-russia-2020/infrastructure-and-public-private-partnerships/key-ppp-legislation">https://cms-law.ru/en/rus/publication/doing-business-in-russia-2020/infrastructure-and-public-private-partnerships/key-ppp-legislation</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0044"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Marques</surname>, <given-names>R</given-names></string-name></person-group>., <year>2018</year>, &#x2018;<article-title>Empirical evidence of unsolicited proposals in PPP arrangements: A comparison of Brazil, Korea and the USA</article-title>&#x2019;, <source><italic>Journal of Comparative Policy Analysis: Research and Practice</italic></source> <volume>20</volume>(<issue>5</issue>), <fpage>435</fpage>&#x2013;<lpage>450</lpage>. <comment><ext-link ext-link-type="uri" xlink:href="https://doi.org/10.1080/13876988.2017.1390866">https://doi.org/10.1080/13876988.2017.1390866</ext-link></comment></mixed-citation></ref>
<ref id="CIT0045"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Meng</surname>, <given-names>L</given-names></string-name>., <string-name><surname>Martinez</surname>, <given-names>R</given-names></string-name>., <string-name><surname>Zhang</surname>, <given-names>J</given-names></string-name>. &#x0026; <string-name><surname>Pan</surname>, <given-names>M</given-names></string-name></person-group>., <year>2015</year>, <source><italic>China&#x2019;s new rules on concession of infrastructure projects: Welcoming private investment</italic></source>, <comment>viewed 22 April 2019, from <ext-link ext-link-type="uri" xlink:href="https://www.haynesboone.com/-/media/files/alert-pdfs/2015/chinasnewrulesoninfrastructurefranchising.ashx?la=en&#x0026;hash=910BE64C9FFC3A81D4409F0A17123F9FDA50C3A7">https://www.haynesboone.com/-/media/files/alert-pdfs/2015/chinasnewrulesoninfrastructurefranchising.ashx?la=en&#x0026;hash=910BE64C9FFC3A81D4409F0A17123F9FDA50C3A7</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0046"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Mouraviev</surname>, <given-names>N</given-names></string-name>. &#x0026; <string-name><surname>Kakabadse</surname>, <given-names>N</given-names></string-name></person-group>., <year>2014</year>, &#x2018;<article-title>Public&#x2013;private partnerships in Russia: Dynamics contributing to an emerging policy paradigm</article-title>&#x2019;, <source><italic>Policy Studies</italic></source> <volume>35</volume>(<issue>1</issue>), <fpage>86</fpage>. <comment><ext-link ext-link-type="uri" xlink:href="https://doi.org/10.1080/01442872.2013.875140">https://doi.org/10.1080/01442872.2013.875140</ext-link></comment></mixed-citation></ref>
<ref id="CIT0047"><mixed-citation publication-type="book"><person-group person-group-type="author"><collab>National Treasury</collab></person-group>, <year>2015</year>, <source><italic>2015 National budget review</italic></source>, <publisher-name>Government Printers</publisher-name>, <publisher-loc>Pretoria</publisher-loc>.</mixed-citation></ref>
<ref id="CIT0048"><mixed-citation publication-type="book"><person-group person-group-type="author"><collab>National Treasury</collab></person-group>, <year>2016</year>, <source><italic>2016 Budget speech, address by the minister of finance on the 24 February 2016, South Africa</italic></source>, <publisher-name>Government Printers</publisher-name>, <publisher-loc>Pretoria</publisher-loc>.</mixed-citation></ref>
<ref id="CIT0049"><mixed-citation publication-type="book"><person-group person-group-type="author"><collab>National Treasury</collab></person-group>, <year>2017</year>, <source><italic>2017 National budget review, South Africa</italic></source>, <publisher-name>Government Printers</publisher-name>, <publisher-loc>Pretoria</publisher-loc>.</mixed-citation></ref>
<ref id="CIT0050"><mixed-citation publication-type="book"><person-group person-group-type="author"><collab>National Treasury</collab></person-group>, <year>2021</year>, &#x2018;<chapter-title>Public private partnerships</chapter-title>&#x2019;, <source><italic>2021 Budget review</italic></source>, <publisher-name>Government Printers</publisher-name>, <publisher-loc>Pretoria</publisher-loc>, <comment>viewed 08 June 2022, from <ext-link ext-link-type="uri" xlink:href="http://www.treasury.gov.za/documents/national&#x0025;20budget/2021/review/Annexure&#x0025;20E.pdf">http://www.treasury.gov.za/documents/national&#x0025;20budget/2021/review/Annexure&#x0025;20E.pdf</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0051"><mixed-citation publication-type="conference"><person-group person-group-type="author"><string-name><surname>Palmer</surname>, <given-names>A</given-names></string-name></person-group>., <year>2015</year>, &#x2018;<article-title>Infrastructure: Developing for the future</article-title>&#x2019;, <conf-name>Presentation held on the 12th January 2015 at the Nanyang Technological University in Singapore, Standard and Poor&#x2019;s Financial Services LLC</conf-name>, <conf-loc>New York, NY</conf-loc>.</mixed-citation></ref>
<ref id="CIT0052"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Pan</surname>, <given-names>R</given-names></string-name></person-group>., <year>n.d.</year>, <source><italic>What is a greenfield project and what are its architectural advantages over a brownfield project?</italic></source>, <comment>viewed 27 July 2020, from <ext-link ext-link-type="uri" xlink:href="https://hmcarchitects.com/news/what-is-a-greenfield-project-advantages-brownfield-project-2019-04-03/">https://hmcarchitects.com/news/what-is-a-greenfield-project-advantages-brownfield-project-2019-04-03/</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0053"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Pereira</surname>, <given-names>A.G</given-names></string-name></person-group>., <year>2014</year>, &#x2018;<article-title>Public-private partnerships (PPP) and concessions of public services in Brazil</article-title>&#x2019;, <source><italic>BRICS Law Journal</italic></source> <volume>1</volume>(<issue>1</issue>), <fpage>25</fpage>&#x2013;<lpage>43</lpage>, <comment>viewed 04 February 2018, from <ext-link ext-link-type="uri" xlink:href="http://www.google.co.za/url?sa=t&#x0026;rct=j&#x0026;q=&#x0026;esrc=s&#x0026;source=web&#x0026;cd=1&#x0026;cad=rja&#x0026;uact=8&#x0026;ved=0ahUKEwjv18nO9ozZAhXPasAKHbHqCA8QFggoMAA&#x0026;url=http&#x0025;3A&#x0025;2F&#x0025;2Fwww.bricslawjournal.com&#x0025;2Fjour&#x0025;2Farticle&#x0025;2Fdownload&#x0025;2F4&#x0025;2F5&#x0026;usg=AOvVaw0gTtWZJi3gYhHEGU6bKP_J">http://www.google.co.za/url?sa=t&#x0026;rct=j&#x0026;q=&#x0026;esrc=s&#x0026;source=web&#x0026;cd=1&#x0026;cad=rja&#x0026;uact=8&#x0026;ved=0ahUKEwjv18nO9ozZAhXPasAKHbHqCA8QFggoMAA&#x0026;url=http&#x0025;3A&#x0025;2F&#x0025;2Fwww.bricslawjournal.com&#x0025;2Fjour&#x0025;2Farticle&#x0025;2Fdownload&#x0025;2F4&#x0025;2F5&#x0026;usg=AOvVaw0gTtWZJi3gYhHEGU6bKP_J</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0054"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Perera</surname>, <given-names>W.S.L</given-names></string-name></person-group>., <year>2016</year>, &#x2018;<article-title>Identify current deficiencies in public private partnership practices and areas which resist PPP being an attractive investment model in infrastructure developments &#x2013; Case study from Sri Lanka</article-title>&#x2019;, <source><italic>International Journal of Engineering Research and Application</italic></source> <volume>6</volume>(<issue>8</issue>), <fpage>14</fpage>&#x2013;<lpage>20</lpage>, <comment>viewed 04 May 2018, from <ext-link ext-link-type="uri" xlink:href="http://ac.els-cdn.com/S1877705816342291/1-s2.0-S1877705816342291-main.pdf?_tid=9593e738-35a7-11e7-a20a-00000aab0f26&#x0026;acdnat=1494438134_cdbe9da5cafe14581d11ac6e52f0980c">http://ac.els-cdn.com/S1877705816342291/1-s2.0-S1877705816342291-main.pdf?_tid=9593e738-35a7-11e7-a20a-00000aab0f26&#x0026;acdnat=1494438134_cdbe9da5cafe14581d11ac6e52f0980c</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0055"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Polyakova</surname>, <given-names>I</given-names></string-name>. &#x0026; <string-name><surname>Vasilyeva</surname>, <given-names>E</given-names></string-name></person-group>., <year>2016</year>, &#x2018;<article-title>Benefits of public-and-private partnership for the creation of the infrastructure of the urbanized territories in Russia</article-title>&#x2019;, <source><italic>Procedia Engineering</italic></source> <volume>165</volume>, <fpage>1380</fpage>&#x2013;<lpage>1387</lpage>. <comment><ext-link ext-link-type="uri" xlink:href="https://doi.org/10.1016/j.proeng.2016.11.868">https://doi.org/10.1016/j.proeng.2016.11.868</ext-link></comment></mixed-citation></ref>
<ref id="CIT0056"><mixed-citation publication-type="book"><person-group person-group-type="author"><collab>Public Private Infrastructure Advisory Facility</collab></person-group>, <year>2017</year>, <source><italic>Who sponsors infrastructure projects?: Disentangling public and private contributions</italic></source>, <publisher-name>World Bank Publications</publisher-name>, <publisher-loc>Washington, DC</publisher-loc>.</mixed-citation></ref>
<ref id="CIT0057"><mixed-citation publication-type="book"><person-group person-group-type="author"><string-name><surname>Queiroz</surname>, <given-names>C</given-names></string-name>., <string-name><surname>Astesiano</surname>, <given-names>G</given-names></string-name>. &#x0026; <string-name><surname>Serebrisky</surname>, <given-names>T</given-names></string-name></person-group>., <year>2014</year>, <source><italic>An overview of the Brazilian PPP experience from a stakeholders&#x2019; viewpoint</italic></source>, <publisher-name>Inter-American Development Bank</publisher-name>, <publisher-loc>Washington DC</publisher-loc>, <comment>viewed 08 June 2022, from <ext-link ext-link-type="uri" xlink:href="https://publications.iadb.org/publications/english/document/An-Overview-of-the-Brazilian-PPP-Experience-from-a-Stakeholders-Viewpoint.pdf">https://publications.iadb.org/publications/english/document/An-Overview-of-the-Brazilian-PPP-Experience-from-a-Stakeholders-Viewpoint.pdf</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0058"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Rehman</surname>, <given-names>A</given-names></string-name></person-group>., <year>2013</year>, <source><italic>A detailed study of environmental constraints faced by public private partnership (PPP) and the road to a framework for successful implementation of PPP projects in India (with special reference to Uttar Pradesh)</italic></source>, <comment>viewed 28 July 2020, from <ext-link ext-link-type="uri" xlink:href="https://sg.inflibnet.ac.in/bitstream/10603/50293/1/01_title.pdf">https://sg.inflibnet.ac.in/bitstream/10603/50293/1/01_title.pdf</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0059"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Sanghai</surname>, <given-names>S</given-names></string-name></person-group>., <year>2021</year>, <source><italic>Can DFI be solution for long-term greenfield infra project financing?</italic></source>, <comment>viewed 05 May 2022, from <ext-link ext-link-type="uri" xlink:href="https://economictimes.indiatimes.com/markets/stocks/news/can-dfi-be-solution-for-long-term-greenfield-infra-project-financing/articleshow/80208627.cms">https://economictimes.indiatimes.com/markets/stocks/news/can-dfi-be-solution-for-long-term-greenfield-infra-project-financing/articleshow/80208627.cms</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0060"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Sanni</surname>, <given-names>A.O</given-names></string-name>. &#x0026; <string-name><surname>Hashim</surname>, <given-names>M</given-names></string-name></person-group>., <year>2014</year>, &#x2018;<article-title>Building infrastructure through public private partnerships in sub-Saharan Africa: Lessons from South Africa</article-title>&#x2019;, <source><italic>Procedia-Social and Behavioral Sciences</italic></source> <volume>143</volume>, <fpage>133</fpage>&#x2013;<lpage>138</lpage>. <comment><ext-link ext-link-type="uri" xlink:href="https://doi.org/10.1016/j.sbspro.2014.07.374">https://doi.org/10.1016/j.sbspro.2014.07.374</ext-link></comment></mixed-citation></ref>
<ref id="CIT0061"><mixed-citation publication-type="book"><person-group person-group-type="author"><string-name><surname>Saunders</surname>, <given-names>M</given-names></string-name>., <string-name><surname>Lewis</surname>, <given-names>P</given-names></string-name>. &#x0026; <string-name><surname>Thornhill</surname>, <given-names>A</given-names></string-name></person-group>., <year>2009</year>, <source><italic>Research methods for business students</italic></source>, <edition>5th</edition> edn., <publisher-name>Pearson Education Limited</publisher-name>, <publisher-loc>Essex</publisher-loc>.</mixed-citation></ref>
<ref id="CIT0062"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Sinkala</surname>, <given-names>A</given-names></string-name>., <string-name><surname>Ochieng</surname>, <given-names>E</given-names></string-name>., <string-name><surname>Ominde</surname>, <given-names>D</given-names></string-name>., <string-name><surname>Zuofa</surname>, <given-names>T</given-names></string-name>. &#x0026; <string-name><surname>Badi</surname>, <given-names>S</given-names></string-name></person-group>., <year>2021</year>, &#x2018;<article-title>Reimagining public-private partnership model as hybrid: South Africa viewpoint</article-title>&#x2019;, <source><italic>Public Works Management &#x0026; Policy</italic></source> <volume>27</volume>(<issue>2</issue>), <fpage>152</fpage>&#x2013;<lpage>183</lpage>. <comment><ext-link ext-link-type="uri" xlink:href="https://doi.org/10.1177/1087724X211046626">https://doi.org/10.1177/1087724X211046626</ext-link></comment></mixed-citation></ref>
<ref id="CIT0063"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Stanley</surname>, <given-names>J</given-names></string-name>. &#x0026; <string-name><surname>David</surname>, <given-names>A</given-names></string-name></person-group>., <year>2008</year>, &#x2018;<article-title>Delivering trusting partnerships for route bus services: A Melbourne case study</article-title>&#x2019;, <source><italic>Transportation Research Part A: Policy and Practice</italic></source> <volume>42</volume>(<issue>10</issue>), <fpage>1295</fpage>&#x2013;<lpage>1301</lpage>. <comment><ext-link ext-link-type="uri" xlink:href="https://doi.org/10.1016/J.TRA.2008.05.006">https://doi.org/10.1016/J.TRA.2008.05.006</ext-link></comment></mixed-citation></ref>
<ref id="CIT0064"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Tan</surname>, <given-names>J</given-names></string-name>. &#x0026; <string-name><surname>Zhao</surname>, <given-names>J.Z</given-names></string-name></person-group>., <year>2019</year>, &#x2018;<article-title>The rise of public-private partnerships in China: An effective financing approach for infrastructure investment?</article-title>&#x2019;, <source><italic>Public Administration Review</italic></source> <volume>79</volume>(<issue>4</issue>), <fpage>514</fpage>&#x2013;<lpage>518</lpage>. <comment><ext-link ext-link-type="uri" xlink:href="https://doi.org/10.1111/puar.13046">https://doi.org/10.1111/puar.13046</ext-link></comment></mixed-citation></ref>
<ref id="CIT0065"><mixed-citation publication-type="book"><person-group person-group-type="author"><string-name><surname>Taruvinga</surname>, <given-names>T.P</given-names></string-name></person-group>., <year>2017</year>, <source><italic>Risk allocation on public private partnership projects</italic></source>, <publisher-name>University of Johannesburg</publisher-name>, <publisher-loc>Johannesburg</publisher-loc>, <comment>viewed 28 September 2018, from <ext-link ext-link-type="uri" xlink:href="http://hdl.handle.net/10210/242418">http://hdl.handle.net/10210/242418</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0066"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Telang</surname>, <given-names>V</given-names></string-name>. &#x0026; <string-name><surname>Kutumbale</surname>, <given-names>V</given-names></string-name></person-group>., <year>2014</year>, <source><italic>Public private partnerships in India (an overview of current scenario)</italic></source>, <comment>viewed 06 February 2018, from <ext-link ext-link-type="uri" xlink:href="https://www.researchgate.net/publication/281024752_PUBLIC_PRIVATE_PARTNERSHIPS_IN_INDIA_An_Overview_of_Current_Scenario">https://www.researchgate.net/publication/281024752_PUBLIC_PRIVATE_PARTNERSHIPS_IN_INDIA_An_Overview_of_Current_Scenario</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0067"><mixed-citation publication-type="journal"><person-group person-group-type="author"><collab>The Africa Report</collab></person-group>, <year>2014</year>, <source><italic>Should Africa establish its own credit ratings agency?</italic></source>, <comment>viewed 10 November 2018, from <ext-link ext-link-type="uri" xlink:href="https://www.theafricareport.com/3918/should-africa-establish-its-own-credit-ratings-agency/amp/">https://www.theafricareport.com/3918/should-africa-establish-its-own-credit-ratings-agency/amp/</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0068"><mixed-citation publication-type="journal"><person-group person-group-type="author"><collab>The Presidency</collab></person-group>, <year>2020</year>, <source><italic>President Cyril Ramaphosa: Meeting with leaders of developmental finance institutions</italic></source>, <comment>viewed 10 October 2020, from <ext-link ext-link-type="uri" xlink:href="https://www.gov.za/speeches/development-finance-institutions-18-feb-2020-0000">https://www.gov.za/speeches/development-finance-institutions-18-feb-2020-0000</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0069"><mixed-citation publication-type="book"><person-group person-group-type="author"><string-name><surname>Thieriot</surname>, <given-names>H</given-names></string-name>. &#x0026; <string-name><surname>Dominguez</surname>, <given-names>C</given-names></string-name></person-group>., <year>2015</year>, <source><italic>Public-private partnerships in China</italic></source>, <comment>Discussion paper</comment>, <publisher-name>International Institute for Sustainable Development</publisher-name>, <publisher-loc>Winnipeg</publisher-loc>, <comment>viewed 04 August 2018, from <ext-link ext-link-type="uri" xlink:href="http://iisd.org/sites/default/files/publications/public-private-partnerships-china.pdf">http://iisd.org/sites/default/files/publications/public-private-partnerships-china.pdf</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0070"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Thillai</surname>, <given-names>R</given-names></string-name>., <string-name><surname>Deep</surname>, <given-names>A</given-names></string-name>. &#x0026; <string-name><surname>Mangu</surname>, <given-names>S</given-names></string-name></person-group>., <year>2018</year>, <source><italic>Opinion: The conundrum of PPP road projects</italic></source>, <comment>viewed 11 July 2020, from <ext-link ext-link-type="uri" xlink:href="https://www.livemint.com/Opinion/ZfpXfkS6Q8NO45hGV26NlM/Opinion--The-conundrum-of-PPP-road-projects.html">https://www.livemint.com/Opinion/ZfpXfkS6Q8NO45hGV26NlM/Opinion--The-conundrum-of-PPP-road-projects.html</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0071"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Thomassen</surname>, <given-names>K</given-names></string-name>., <string-name><surname>Vassb&#x00F8;</surname>, <given-names>S</given-names></string-name>., <string-name><surname>Solheim-Kile</surname>, <given-names>E</given-names></string-name>. &#x0026; <string-name><surname>Lohne</surname>, <given-names>J</given-names></string-name></person-group>., <year>2016</year>, &#x2018;<article-title>Public-private partnership: Transaction costs of tendering</article-title>&#x2019;, <source><italic>Procedia Computer Science</italic></source> <volume>100</volume>, <fpage>818</fpage>&#x2013;<lpage>825</lpage>. <comment><ext-link ext-link-type="uri" xlink:href="https://doi.org/10.1016/j.procs.2016.09.230">https://doi.org/10.1016/j.procs.2016.09.230</ext-link></comment></mixed-citation></ref>
<ref id="CIT0072"><mixed-citation publication-type="conference"><person-group person-group-type="author"><string-name><surname>Tiong</surname>, <given-names>R</given-names></string-name></person-group>., <year>2013</year>, &#x2018;<article-title>Public private partnerships (PPP) &#x2013; Policy, regulation, legal frameworks for PPP developments</article-title>&#x2019;, Presentation from the <conf-name>Singapore MFA Programme on PPP</conf-name> held from the <conf-date>16&#x2013;15 October 2013</conf-date>, <conf-loc>Nanyang Technological University (School of Civil and Environmental Engineering), Singapore</conf-loc>.</mixed-citation></ref>
<ref id="CIT0073"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Walwyn</surname>, <given-names>D.R</given-names></string-name>. &#x0026; <string-name><surname>Nkolele</surname>, <given-names>A.T</given-names></string-name></person-group>., <year>2018</year>, &#x2018;<article-title>An evaluation of South Africa&#x2019;s public-private partnership for the localisation of vaccine research, manufacture and distribution</article-title>&#x2019;, <source><italic>Health Research Policy &#x0026; Systems</italic></source> <volume>16</volume>, <fpage>1</fpage>. <comment><ext-link ext-link-type="uri" xlink:href="https://doi.org/10.1186/s12961-018-0303-3">https://doi.org/10.1186/s12961-018-0303-3</ext-link></comment></mixed-citation></ref>
<ref id="CIT0074"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Wei</surname>, <given-names>L</given-names></string-name>., <string-name><surname>Wenjuan</surname>, <given-names>L</given-names></string-name>. &#x0026; <string-name><surname>Xu</surname>, <given-names>X</given-names></string-name></person-group>., <year>2015</year>, &#x2018;<article-title>The analysis of the PPP financing model application in ports of China</article-title>&#x2019;, <source><italic>Journal of Coastal Research</italic></source> <volume>73</volume>(<supplement>suppl. 1</supplement>), <fpage>4</fpage>&#x2013;<lpage>8</lpage>. <comment><ext-link ext-link-type="uri" xlink:href="https://doi.org/10.2112/SI73-002.1">https://doi.org/10.2112/SI73-002.1</ext-link></comment></mixed-citation></ref>
<ref id="CIT0075"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Wheat</surname>, <given-names>P</given-names></string-name>., <string-name><surname>Stead</surname>, <given-names>A.D</given-names></string-name>., <string-name><surname>Huang</surname>, <given-names>Y</given-names></string-name>. &#x0026; <string-name><surname>Smith</surname>, <given-names>A</given-names></string-name></person-group>., <year>2019</year>, &#x2018;<article-title>Lowering transport costs and prices by competition: Regulatory and institutional reforms in low income countries</article-title>&#x2019;, <source><italic>Sustainability</italic></source> <volume>11</volume>, <year>5940</year>. <comment><ext-link ext-link-type="uri" xlink:href="https://doi.org/10.3390/su11215940">https://doi.org/10.3390/su11215940</ext-link></comment></mixed-citation></ref>
<ref id="CIT0076"><mixed-citation publication-type="journal"><person-group person-group-type="author"><string-name><surname>Withrington</surname>, <given-names>P</given-names></string-name></person-group>., <year>2011</year>, <source><italic>Road versus rail</italic></source>, <comment>viewed 20 June 2020, from <ext-link ext-link-type="uri" xlink:href="https://iea.org.uk/blog/rail-versus-road">https://iea.org.uk/blog/rail-versus-road</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0077"><mixed-citation publication-type="book"><person-group person-group-type="author"><collab>World Bank Group (WBG)</collab></person-group>, <year>2013</year>, <source>Disclosure of project and contract information in public-private partnerships</source>, <publisher-name>World Bank Publications</publisher-name>, xylWashington, DC.</mixed-citation></ref>
<ref id="CIT0078"><mixed-citation publication-type="journal"><person-group person-group-type="author"><collab>World Bank Group (WBG)</collab></person-group>, <year>2015a</year>, <source><italic>Organization</italic></source>, <comment>viewed 12 April 2018, from <ext-link ext-link-type="uri" xlink:href="http://www.worldbank.org/en/about/leadership">http://www.worldbank.org/en/about/leadership</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0079"><mixed-citation publication-type="journal"><person-group person-group-type="author"><collab>World Bank Group (WBG)</collab></person-group>, <year>2016</year>, <source><italic>A framework for disclosure in public-private partnerships</italic></source>, <comment>viewed 26 April 2022, from <ext-link ext-link-type="uri" xlink:href="https://thedocs.worldbank.org/en/doc/143671469558797229-0100022016/original/FrameworkPPPDisclosure071416.pdf">https://thedocs.worldbank.org/en/doc/143671469558797229-0100022016/original/FrameworkPPPDisclosure071416.pdf</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0080"><mixed-citation publication-type="journal"><person-group person-group-type="author"><collab>World Bank Group (WBG)</collab></person-group>, <year>2019</year>, <source><italic>Private participation in infrastructure (PPI) database</italic></source>, <comment>viewed 15 February 2018, from <ext-link ext-link-type="uri" xlink:href="https://ppi.worldbank.org/">https://ppi.worldbank.org/</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0081"><mixed-citation publication-type="journal"><person-group person-group-type="author"><collab>World Population Review</collab></person-group>, <year>2019</year>, <source><italic>GDP ranked by country 2022</italic></source>, <comment>viewed 08 June 2022, from <ext-link ext-link-type="uri" xlink:href="https://worldpopulationreview.com/countries/countries-by-gdp">https://worldpopulationreview.com/countries/countries-by-gdp</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0082"><mixed-citation publication-type="book"><person-group person-group-type="author"><collab>World Bank Group (WBG)</collab></person-group>, <year>2020a</year>, <source><italic>Private participation in infrastructure data</italic></source>, <publisher-name>World Bank</publisher-name>, <publisher-loc>Washington, DC</publisher-loc>, <comment>viewed 06 May 2020, from <ext-link ext-link-type="uri" xlink:href="https://ppi.worldbank.org/en/ppidata">https://ppi.worldbank.org/en/ppidata</ext-link>.</comment></mixed-citation></ref>
<ref id="CIT0083"><mixed-citation publication-type="journal"><person-group person-group-type="author"><collab>WSP International Management Consulting</collab></person-group>, <year>n.d.</year>, <source><italic>Public private partnership in India</italic></source>, <comment>viewed 08 June 2022, from <ext-link ext-link-type="uri" xlink:href="https://assets.publishing.service.gov.uk/media/57a08afa40f0b649740008b6/TI_UP_HD_Aug2010_Public_Private_Partnership_in_India.pdf">https://assets.publishing.service.gov.uk/media/57a08afa40f0b649740008b6/TI_UP_HD_Aug2010_Public_Private_Partnership_in_India.pdf</ext-link>.</comment></mixed-citation></ref>
</ref-list>
<fn-group>
<fn><p><bold>How to cite this article:</bold> Sebitlo, O.K., Mbara, T. &#x0026; Luke, R., 2022, &#x2018;The state of South Africa&#x2019;s public&#x2013;private partnership practices in transport projects: Problems and potential, <italic>Journal of Transport and Supply Chain Management</italic> 16(0), a733. <ext-link ext-link-type="uri" xlink:href="https://doi.org/10.4102/jtscm.v16i0.733">https://doi.org/10.4102/jtscm.v16i0.733</ext-link></p></fn>
</fn-group>
</back>